428 1/2 S CHICAGO ST 90033
Certificate Information: 428 1/2 S CHICAGO ST 90033
- Application / Permit
- 24014-10000-03358
- Plan Check / Job No.
- B24LA15556
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT PORTION OF 1ST FLOOR UNIT OF (E) DUPLEX TO ATTACHED ADU WITH ADDITION PER CA GC 66323(a)(1)and 66333, ALL WORK PER WFPP SEE COMMENT
- Permit Issued
- Issued on 1/31/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | MINA HABILI |
| Corrections Issued | 8/3/2024 | MINA HABILI |
| Building Plans Picked Up | 8/7/2024 | APPLICANT |
| Applicant returned to address corrections | 9/24/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 1/7/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 1/31/2025 | DANIEL SANJUAN |
| Issued | 1/31/2025 | APPLICANT |
| CofO in Progress | 1/6/2026 | FREDDIE RIVERA |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
| CofO Issued | 1/9/2026 | DEROLD HAUFF |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/18/2024 | MAYELA VILLA |
| Address approval | Cleared | 9/26/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 9/26/2024 | TREVOR QUAN |
| Clean Up Green Up | Cleared | 10/1/2024 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2024 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 10/2/2024 | ALEXANDER HELFER |
| Sewer availability | Cleared | 10/2/2024 | TREVOR QUAN |
| Tenant Habitability Plan | Cleared | 1/15/2025 | KORNEL LELEA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/10/2025 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 4/10/2025 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 4/10/2025 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 4/10/2025 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/22/2025 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 4/22/2025 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 4/22/2025 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/12/2025 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/12/2025 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/12/2025 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 5/12/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/12/2025 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/22/2025 | No Access for Inspection | FREDDIE RIVERA |
| Green Building Rough | 5/22/2025 | No Access for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 5/22/2025 | No Access for Inspection | FREDDIE RIVERA |
| Special/Order Compliance | 5/22/2025 | No Access for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/29/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/29/2025 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 5/29/2025 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 5/29/2025 | Partial Inspection | FREDDIE RIVERA |
| Special/Order Compliance | 5/29/2025 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/27/2025 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/27/2025 | Approved | FREDDIE RIVERA |
| Green Building Rough | 6/27/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 6/27/2025 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 6/27/2025 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/28/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 7/28/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 7/28/2025 | Corrections Issued | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/28/2025 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 8/5/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/12/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 9/18/2025 | Corrections Issued | FREDDIE RIVERA |
| Final | 9/18/2025 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 9/18/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 9/18/2025 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/18/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 9/18/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 9/18/2025 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 9/18/2025 | Partial Inspection | FREDDIE RIVERA |
| Final | 10/22/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 12/9/2025 | Partial Inspection | FREDDIE RIVERA |
| Final | 12/9/2025 | OK to Issue CofO | FREDDIE RIVERA |
| Special/Order Compliance | 12/9/2025 | Partial Inspection | FREDDIE RIVERA |