10423 S RUTHELEN ST 90047
Certificate Information: 10423 S RUTHELEN ST 90047
- Application / Permit
- 24014-10000-03355
- Plan Check / Job No.
- B24LA15548
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Two-story ground floor addition to (E) one story garage. the addition will be an ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 12/5/2025
- Issuing Office
- Current Status
- Issued on 12/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 9/13/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 9/13/2024 | RODOLFO ARIAS |
| Applicant returned to address corrections | 6/18/2025 | GEORGE JOLAKIAN |
| Plan Check Approved | 8/11/2025 | GEORGE JOLAKIAN |
| Issued | 12/5/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/21/2024 | DAVID LOPEZ |
| Construction near power lines | Cleared | 1/2/2025 | RIDWAN HARDY |
| Address approval | Cleared | 4/2/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/8/2025 | DAVID LOPEZ |
Contact Information
| Contractor | Pacific Point Builders Inc; Lic. No.: 768984-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/22/2025 | Corrections Issued | MICHAEL LEWIS |
| Pre-Inspection | 12/22/2025 | Corrections Issued | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 1/21/2026 | No Access for Inspection | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 1/27/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 2/17/2026 | Corrections Issued | SALVADOR MARTINEZ |
| METHANE-Subgrade | 2/17/2026 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/17/2026 | Partial Approval | SALVADOR MARTINEZ |
| Sewer | 2/17/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 4/3/2026 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 4/20/2026 | Partial Inspection | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 4/20/2026 | Corrections Issued | SALVADOR MARTINEZ |
| METHANE-Barrier | 4/20/2026 | Approved | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 4/24/2026 | Approved | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 4/24/2026 | Approved | SALVADOR MARTINEZ |
| Sewer | 6/8/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 6/10/2026 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/12/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 6/12/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| METHANE-Rough | 6/12/2026 | Approved | SALVADOR MARTINEZ |
| Sewer | 6/12/2026 | Approved | SALVADOR MARTINEZ |
| Wood Frame | 6/12/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2026 | Partial Approval | SALVADOR MARTINEZ |