1454 1/2 W YOSEMITE DR 90041
Certificate Information: 1454 1/2 W YOSEMITE DR 90041
- Application / Permit
- 24014-10000-03349
- Plan Check / Job No.
- B24LA15484
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF (E) GARAGE AND ADDITION TO A DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) (1-STORY)
- Permit Issued
- Issued on 12/10/2024
- Issuing Office
- Current Status
- CofO Issued on 8/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2024 | CARLOS MONTES |
| Corrections Issued | 8/3/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 10/9/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 10/27/2024 | CARLOS MONTES |
| Issued | 12/10/2024 | APPLICANT |
| CofO in Progress | 8/22/2025 | DAVID WILLIAMS |
| Permit Finaled | 8/23/2025 | DEROLD HAUFF |
| CofO Issued | 8/23/2025 | DEROLD HAUFF |
| Permit Finaled | 8/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/7/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 8/7/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2024 | CELINA MORENO |
| Sewer availability | Cleared | 8/8/2024 | CELINA MORENO |
| Watercourse | Cleared | 8/12/2024 | TERRY PHAN |
| Grading Pre-Inspection | Cleared | 10/9/2024 | CARLOS MONTES |
Contact Information
| Contractor | Adu Rc Builders; Lic. No.: 1080967-B | , |
| Contractor | Ca Construction Group Inc; Lic. No.: 1080967-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/22/2025 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 1/22/2025 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 1/22/2025 | Partial Approval | BRENDAN MORELLI |
| Sewer | 1/22/2025 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 1/22/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Drilled-In Anchors | 3/6/2025 | Conditional Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/1/2025 | Conditional Approval | DAVID WILLIAMS |
| ELECTRICAL-Rough | 4/1/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 4/1/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 4/1/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 4/1/2025 | Approved | DAVID WILLIAMS |
| Insulation | 4/29/2025 | Approved | DAVID WILLIAMS |
| Insulation | 4/29/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 4/29/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 5/2/2025 | Approved | DAVID WILLIAMS |
| Deputy Wood Construction | 5/2/2025 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 5/15/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 5/15/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 5/15/2025 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 7/17/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 7/17/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 7/17/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 7/17/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 7/17/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Not Required | ALIZAH MAYAGOITIA |
| Service/Power Release | 7/17/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/17/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 8/15/2025 | Approved | LILIANA PORTILLO |
| Final | 8/15/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 8/15/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 8/15/2025 | Approved | LILIANA PORTILLO |
| Service/Power Release | 8/15/2025 | Approved | LILIANA PORTILLO |
| Final | 8/21/2025 | OK to Issue CofO | DAVID WILLIAMS |
| HVAC-Final | 8/21/2025 | Approved | DAVID WILLIAMS |
| Underground Mechanical | 8/21/2025 | Approved | DAVID WILLIAMS |