1454 1/2 W YOSEMITE DR 90041

Certificate Information: 1454 1/2 W YOSEMITE DR 90041

Application / Permit
24014-10000-03349
Plan Check / Job No.
B24LA15484
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF (E) GARAGE AND ADDITION TO A DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) (1-STORY)
Permit Issued
Issued on 12/10/2024
Issuing Office
Current Status
CofO Issued on 8/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2024 APPLICANT
Assigned to Plan Check Engineer 8/2/2024 CARLOS MONTES
Corrections Issued 8/3/2024 CARLOS MONTES
Applicant returned to address corrections 10/9/2024 JOSEPH RAFOLS
Plan Check Approved 10/27/2024 CARLOS MONTES
Issued 12/10/2024 APPLICANT
CofO in Progress 8/22/2025 DAVID WILLIAMS
Permit Finaled 8/23/2025 DEROLD HAUFF
CofO Issued 8/23/2025 DEROLD HAUFF
Permit Finaled 8/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/7/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 8/7/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/8/2024 CELINA MORENO
Sewer availability Cleared 8/8/2024 CELINA MORENO
Watercourse Cleared 8/12/2024 TERRY PHAN
Grading Pre-Inspection Cleared 10/9/2024 CARLOS MONTES

Contact Information

Contractor Adu Rc Builders; Lic. No.: 1080967-B       ,
Contractor Ca Construction Group Inc; Lic. No.: 1080967-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/22/2025 Approved BRENDAN MORELLI
Footing/Foundation/Slab 1/22/2025 Approved BRENDAN MORELLI
PLUMBING-Rough 1/22/2025 Partial Approval BRENDAN MORELLI
Sewer 1/22/2025 Approved BRENDAN MORELLI
Underground Mechanical 1/22/2025 Partial Approval BRENDAN MORELLI
Deputy Drilled-In Anchors 3/6/2025 Conditional Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 4/1/2025 Conditional Approval DAVID WILLIAMS
ELECTRICAL-Rough 4/1/2025 Approved DAVID WILLIAMS
Green Building Rough 4/1/2025 Approved DAVID WILLIAMS
HVAC-Rough 4/1/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 4/1/2025 Approved DAVID WILLIAMS
Insulation 4/29/2025 Approved DAVID WILLIAMS
Insulation 4/29/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 4/29/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 5/2/2025 Approved DAVID WILLIAMS
Deputy Wood Construction 5/2/2025 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Approved DAVID WILLIAMS
Drywall Nailing 5/15/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 5/15/2025 Approved REGINA MENDEZ
Shower Pan 5/15/2025 Approved REGINA MENDEZ
ELECTRICAL-Final 7/17/2025 Corrections Issued ALIZAH MAYAGOITIA
Final 7/17/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 7/17/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 7/17/2025 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 7/17/2025 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/17/2025 SGSOV Not Required ALIZAH MAYAGOITIA
Service/Power Release 7/17/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 7/17/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 8/15/2025 Approved LILIANA PORTILLO
Final 8/15/2025 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 8/15/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 8/15/2025 Approved LILIANA PORTILLO
Service/Power Release 8/15/2025 Approved LILIANA PORTILLO
Final 8/21/2025 OK to Issue CofO DAVID WILLIAMS
HVAC-Final 8/21/2025 Approved DAVID WILLIAMS
Underground Mechanical 8/21/2025 Approved DAVID WILLIAMS