3532-3532 1/2 E 4TH ST 90063
Certificate Information: 3532-3532 1/2 E 4TH ST 90063
- Application / Permit
- 24014-10000-03346
- Plan Check / Job No.
- B24LA15476
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: Convert the existing SFD into a new Duplex with an addition.
- Permit Issued
- Issued on 12/5/2024
- Issuing Office
- Current Status
- CofO Issued on 12/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 8/17/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/22/2024 | YOUNG KIM |
| Plan Check Approved | 12/4/2024 | ARSALAN SHABESTARI |
| Issued | 12/5/2024 | APPLICANT |
| CofO in Progress | 12/26/2025 | FREDDIE RIVERA |
| Permit Finaled | 12/27/2025 | DEROLD HAUFF |
| Permit Finaled | 12/27/2025 | DEROLD HAUFF |
| CofO Issued | 12/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/22/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 8/22/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 8/22/2024 | JUSTIN BICOL |
| Clean Up Green Up | Cleared | 9/26/2024 | JACQUELINE TORRES |
| ZI | Cleared | 9/26/2024 | JACQUELINE TORRES |
| ZI | Cleared | 10/2/2024 | JACQUELINE TORRES |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/9/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 12/10/2024 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 12/10/2024 | Partial Inspection | FREDDIE RIVERA |
| Verify Rec and Parks Fee Memo | 12/10/2024 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Partial Approval | FREDDIE RIVERA |
| Insulation | 12/23/2024 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/27/2025 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Partial Approval | FREDDIE RIVERA |
| Verify Rec and Parks Fee Memo | 1/27/2025 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/29/2025 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/29/2025 | Approved | FREDDIE RIVERA |
| Green Building Rough | 1/29/2025 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Rough | 1/29/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 1/29/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/6/2025 | Approved | FREDDIE RIVERA |
| Green Building Rough | 2/6/2025 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 2/6/2025 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 2/10/2025 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/27/2025 | Approved | FREDDIE RIVERA |
| Sewer | 2/27/2025 | Approved | FREDDIE RIVERA |
| Verify Rec and Parks Fee Memo | 6/17/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 9/15/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Final | 9/15/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Final | 9/15/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 9/23/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/23/2025 | Approved | FREDDIE RIVERA |
| Green Building Final | 9/23/2025 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 9/23/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/23/2025 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 9/23/2025 | Approved | FREDDIE RIVERA |
| Final | 9/29/2025 | OK to Issue CofO | FREDDIE RIVERA |
| Final | 10/20/2025 | Corrections Issued | JUSTIN HAWLEY |