5900 W 74TH ST 90045
Certificate Information: 5900 W 74TH ST 90045
- Application / Permit
- 24014-10000-03337
- Plan Check / Job No.
- B24LA15419
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. NFPA 13D FIRE SPRINKLERS REQUIRED. NEW IRREGULAR SHAPED ADDITION AND REMODEL OF EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE PER ENGINEER. COMPLY WITH DEPARTMENT ORDER effective date 08/05/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 8/30/2024
- Issuing Office
- Current Status
- CofO in Progress on 4/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 8/6/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 8/23/2024 | KEVIN MORALES |
| Plan Check Approved | 8/29/2024 | KEVIN MORALES |
| Issued | 8/30/2024 | APPLICANT |
| CofO in Progress | 4/5/2025 | ANDREW BEELI |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/16/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 8/25/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2024 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 8/26/2024 | VASIL MIHALEV |
| Specific Plan | Cleared | 8/27/2024 | PEDRO AYALA |
| GPI Written Notices | Cleared | 8/29/2024 | DANIEL ABRAMYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/19/2024 | Approved | ANDREW BEELI |
| Excavation/Setback/Form/Re-Bar | 9/19/2024 | Approved | ANDREW BEELI |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Rough | 9/25/2024 | Corrections Issued | ANDREW BEELI |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 9/26/2024 | Partial Approval | ANDREW BEELI |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Partial Approval | ANDREW BEELI |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2024 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 10/10/2024 | Not Ready for Inspection | ANDREW BEELI |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Corrections Issued | ANDREW BEELI |
| HVAC-Rough | 10/17/2024 | Not Ready for Inspection | ANDREW BEELI |
| HVAC-Rough | 10/31/2024 | Approved | ANDREW BEELI |
| Interior/Exterior Lathing | 10/31/2024 | Not Ready for Inspection | ANDREW BEELI |
| Interior/Exterior Lathing | 11/6/2024 | Approved | RYAN BARNES |
| ELECTRICAL-Rough | 11/7/2024 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 11/7/2024 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 11/12/2024 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 11/12/2024 | Approved | ANDREW BEELI |
| Service/Power Release | 11/12/2024 | Approved | ANDREW BEELI |
| Insulation | 11/14/2024 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 11/20/2024 | Approved | ANDREW BEELI |
| Drywall Nailing | 11/20/2024 | Approved | ANDREW BEELI |
| Insulation | 11/20/2024 | Approved | ANDREW BEELI |
| Interior/Exterior Lathing | 11/20/2024 | Approved | ANDREW BEELI |
| MERV13>=Rough | 11/20/2024 | Approved | ANDREW BEELI |
| Final | 2/14/2025 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 2/14/2025 | Approved | ANDREW BEELI |
| MERV13>=Final | 2/14/2025 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Approved | ANDREW BEELI |
| Smoke Detectors | 2/14/2025 | Approved | ANDREW BEELI |
| Final | 4/1/2025 | Corrections Issued | ANDREW BEELI |
| MERV13>=Final | 4/1/2025 | Approved | ANDREW BEELI |
| ELECTRICAL-Final | 4/3/2025 | Not Ready for Inspection | ANDREW BEELI |
| Final | 4/3/2025 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Final | 4/3/2025 | Approved | ANDREW BEELI |
| HVAC-Final | 4/3/2025 | Approved | ANDREW BEELI |
| PLUMBING-Final | 4/3/2025 | Approved | ANDREW BEELI |
| Verify Sprinkler Sign Off | 4/3/2025 | Approved | ANDREW BEELI |
| ELECTRICAL-Final | 4/4/2025 | Approved | ANDREW BEELI |
| Final | 4/4/2025 | OK to Issue CofO | ANDREW BEELI |