3637 N LOADSTONE DR 91403

Certificate Information: 3637 N LOADSTONE DR 91403

Application / Permit
24014-10000-03331
Plan Check / Job No.
B24LA15389
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] Remodel and Ground Addition to (E) 1-Story Single Family Dwelling with Attached 2-car Garage.
Permit Issued
Issued on 12/5/2024
Issuing Office
Current Status
CofO Issued on 8/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 KHEDER ALRAZAA
Corrections Issued 8/13/2024 KHEDER ALRAZAA
Quality Review Completed 8/14/2024 GARO TELMI
Applicant returned to address corrections 11/22/2024 KHEDER ALRAZAA
Plan Check Approved 12/5/2024 KHEDER ALRAZAA
Issued 12/5/2024 APPLICANT
CofO in Progress 7/30/2025 JUAN VALENZUELA
Permit Finaled 8/14/2025 RUBEN SALAS
CofO Issued 8/14/2025 RUBEN SALAS
Permit Finaled 8/14/2025 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/21/2024 RYAN CASTRO
BHO/Hillside ordinance Cleared 8/21/2024 RYAN CASTRO
BHO/Hillside ordinance Cleared 8/21/2024 RYAN CASTRO
BHO/Hillside ordinance Cleared 8/21/2024 RYAN CASTRO
BHO/Hillside ordinance Cleared 8/21/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/21/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 8/21/2024 RYAN CASTRO
Sewer availability Cleared 8/21/2024 RYAN CASTRO
Grading Pre-Inspection Cleared 8/30/2024 CHARLES POWELL
Specific Plan Cleared 11/12/2024 TIFFANY CORRALES

Contact Information

Contractor Owner-Builder       ,
Engineer Mangoli,, Arash; Lic. No.: C84319 1727 BENTLEY AVE APT 211      LOS ANGELES, CA 90025

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/6/2024 Approved JACK KARGODORIAN
Deputy Drilled-In Anchors 12/19/2024 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 12/23/2024 Approved JACK KARGODORIAN
Deputy Wood Construction 1/28/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 1/30/2025 Corrections Issued JACK KARGODORIAN
Deputy Drilled-In Anchors 1/30/2025 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 2/21/2025 Corrections Issued JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 2/21/2025 Partial Approval JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 2/27/2025 Approved JACK KARGODORIAN
Wood Frame 2/27/2025 Approved JACK KARGODORIAN
Insulation 3/10/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 3/10/2025 Partial Approval JACK KARGODORIAN
Drywall Nailing 3/17/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 3/17/2025 Approved JACK KARGODORIAN
Service/Power Release 3/28/2025 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 7/23/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 7/23/2025 Approved JAVIER RAMOS JR
Final 7/23/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 7/23/2025 Approved JAVIER RAMOS JR
HVAC-Final 7/23/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 7/23/2025 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 7/23/2025 Approved JAVIER RAMOS JR
Smoke Detectors 7/23/2025 Approved JAVIER RAMOS JR
Final 7/29/2025 OK to Issue CofO JUAN VALENZUELA
HVAC-Final 7/29/2025 Approved JUAN VALENZUELA
PLUMBING-Final 7/29/2025 Approved JUAN VALENZUELA