3637 N LOADSTONE DR 91403
Certificate Information: 3637 N LOADSTONE DR 91403
- Application / Permit
- 24014-10000-03331
- Plan Check / Job No.
- B24LA15389
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [ePlan] Remodel and Ground Addition to (E) 1-Story Single Family Dwelling with Attached 2-car Garage.
- Permit Issued
- Issued on 12/5/2024
- Issuing Office
- Current Status
- CofO Issued on 8/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | KHEDER ALRAZAA |
| Corrections Issued | 8/13/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 8/14/2024 | GARO TELMI |
| Applicant returned to address corrections | 11/22/2024 | KHEDER ALRAZAA |
| Plan Check Approved | 12/5/2024 | KHEDER ALRAZAA |
| Issued | 12/5/2024 | APPLICANT |
| CofO in Progress | 7/30/2025 | JUAN VALENZUELA |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
| CofO Issued | 8/14/2025 | RUBEN SALAS |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/21/2024 | RYAN CASTRO |
| BHO/Hillside ordinance | Cleared | 8/21/2024 | RYAN CASTRO |
| BHO/Hillside ordinance | Cleared | 8/21/2024 | RYAN CASTRO |
| BHO/Hillside ordinance | Cleared | 8/21/2024 | RYAN CASTRO |
| BHO/Hillside ordinance | Cleared | 8/21/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/21/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 8/21/2024 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 8/30/2024 | CHARLES POWELL |
| Specific Plan | Cleared | 11/12/2024 | TIFFANY CORRALES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mangoli,, Arash; Lic. No.: C84319 | 1727 BENTLEY AVE APT 211 LOS ANGELES, CA 90025 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/6/2024 | Approved | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 12/19/2024 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 12/23/2024 | Approved | JACK KARGODORIAN |
| Deputy Wood Construction | 1/28/2025 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 1/30/2025 | Corrections Issued | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 1/30/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 2/21/2025 | Corrections Issued | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 2/21/2025 | Partial Approval | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 2/27/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 2/27/2025 | Approved | JACK KARGODORIAN |
| Insulation | 3/10/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/10/2025 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 3/17/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/17/2025 | Approved | JACK KARGODORIAN |
| Service/Power Release | 3/28/2025 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/23/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/23/2025 | Approved | JAVIER RAMOS JR |
| Final | 7/23/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 7/23/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 7/23/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 7/23/2025 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 7/23/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 7/23/2025 | Approved | JAVIER RAMOS JR |
| Final | 7/29/2025 | OK to Issue CofO | JUAN VALENZUELA |
| HVAC-Final | 7/29/2025 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 7/29/2025 | Approved | JUAN VALENZUELA |