5324 S HILLCREST DR 90043
Certificate Information: 5324 S HILLCREST DR 90043
- Application / Permit
- 24014-10000-03327
- Plan Check / Job No.
- B24LA15336
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Rear addition and remodel to existing 1 story SFD. Work per engineer design.
- Permit Issued
- Issued on 9/13/2024
- Issuing Office
- Current Status
- CofO Issued on 4/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | ADAM HEGAZI |
| Corrections Issued | 8/17/2024 | ADAM HEGAZI |
| Plan Check Approved | 8/28/2024 | ADAM HEGAZI |
| Issued | 9/13/2024 | APPLICANT |
| CofO in Progress | 4/21/2026 | LUIS CASTRO |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
| CofO Issued | 4/26/2026 | DEROLD HAUFF |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/23/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2024 | JUSTIN BICOL |
Contact Information
| Architect | Mahlebashian,, Robert Mihran; Lic. No.: NA23372 | , |
| Contractor | C C C Construction Inc; Lic. No.: 681028-B | , |
| Engineer | Yap,, George; Lic. No.: C94875 | 14 SILVERWOOD IRVINE, CA 92604 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/5/2024 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2024 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 12/27/2024 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 1/3/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 1/6/2025 | Partial Approval | LUIS CASTRO |
| Deputy Drilled-In Anchors | 1/10/2025 | Partial Approval | LUIS CASTRO |
| Deputy Wood Construction | 1/10/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 2/14/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 2/14/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 2/14/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 2/14/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 2/21/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 2/26/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 2/27/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 3/3/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 3/3/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 11/19/2025 | Approved | LUIS CASTRO |
| Final | 11/19/2025 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 11/19/2025 | Approved | LUIS CASTRO |
| Green Building Final | 11/19/2025 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Rough | 11/19/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 11/19/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 11/19/2025 | Approved | LUIS CASTRO |
| Final | 2/4/2026 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Final | 2/4/2026 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Final | 4/20/2026 | Approved | LUIS CASTRO |
| Final | 4/20/2026 | OK to Issue CofO | LUIS CASTRO |
| Green Building Final | 4/20/2026 | Approved | LUIS CASTRO |
| HVAC-Final | 4/20/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/20/2026 | Approved | LUIS CASTRO |