Work Description
(ePLAN) 2nd story accessory dwelling unit addition over existing garage with attached trellis per LAMC 12.22 A.33(b)(1). Work per engineer details.
Permit Issued
Issued on 8/21/2025
Issuing Office
Current Status
Issued on 8/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 VICTOR CHEN
Corrections Issued 8/7/2024 VICTOR CHEN
Quality Review Completed 8/16/2024 YOUNG KIM
Applicant returned to address corrections 3/24/2025 VICTOR CHEN
Applicant returned to address corrections 5/7/2025 VICTOR CHEN
Applicant returned to address corrections 6/3/2025 VICTOR CHEN
Plan Check Approved 6/12/2025 VICTOR CHEN
Issued 8/21/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/8/2024 ABEL CASILLAS
Roof/Waste drainage to street Cleared 11/8/2024 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 11/16/2024 ABEL CASILLAS
Sewer availability Cleared 11/16/2024 ABEL CASILLAS
Construction near power lines Cleared 2/12/2025 RIDWAN HARDY

Contact Information

Architect Eckelberry,, Anthony Evans; Lic. No.: C17278 4535 GAINSBOROUGH AVE.      LOS ANGELES, CA 90027
Contractor Butel Construction Inc; Lic. No.: 852273-B       ,
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 347 ROBERTSON BLVD      BEVERLY HILLS, CA 90211
Engineer Gonzalez,, Fernando Francisco; Lic. No.: C53256 11607 AMESTOY AVE      GRANADA HILLS, CA 91344
Engineer Gonzalez,, Fernando Francisco; Lic. No.: NA53256       ,

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/26/2025 Corrections Issued RAUL BARAJAS
METHANE-Rough 9/26/2025 Not Ready for Inspection RAUL BARAJAS
Underground Mechanical 9/26/2025 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 11/3/2025 Not Ready for Inspection JOSH MEISTER
METHANE-Barrier 11/3/2025 Not Ready for Inspection JOSH MEISTER
METHANE-Rough 11/3/2025 Not Ready for Inspection JOSH MEISTER
METHANE-Subgrade 11/3/2025 Not Ready for Inspection JOSH MEISTER
Sewer 11/3/2025 Not Ready for Inspection JOSH MEISTER
Excavation/Setback/Form/Re-Bar 12/12/2025 Corrections Issued JOSH MEISTER
Excavation/Setback/Form/Re-Bar 12/19/2025 Partial Inspection JOSH MEISTER
Footing/Foundation/Slab 1/17/2026 Not Ready for Inspection DANIEL VERA
Footing/Foundation/Slab 1/20/2026 Approved JOSH MEISTER
METHANE-Barrier 1/20/2026 Approved JOSH MEISTER
METHANE-Subgrade 1/20/2026 Approved JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 2/13/2026 Partial Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 3/27/2026 Corrections Issued JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 3/31/2026 Approved JOSH MEISTER
BUILDING-Rough-Frame 4/16/2026 Not Ready for Inspection JOSH MEISTER
ELECTRICAL-Rough 4/16/2026 Corrections Issued JOSH MEISTER
Green Building Rough 4/16/2026 Approved JOSH MEISTER
HVAC-Rough 4/16/2026 Corrections Issued JOSH MEISTER
Interior/Exterior Lathing 4/16/2026 Approved JOSH MEISTER
METHANE-Rough 4/16/2026 Approved JOSH MEISTER
PLUMBING-Rough 4/16/2026 Corrections Issued JOSH MEISTER
BUILDING-Rough-Frame 4/22/2026 Approved JOSH MEISTER
ELECTRICAL-Rough 4/22/2026 Approved JOSH MEISTER
HVAC-Rough 4/22/2026 Approved JOSH MEISTER
PLUMBING-Rough 4/22/2026 Approved JOSH MEISTER
Insulation 5/7/2026 Approved JOSH MEISTER
Drywall Nailing 5/21/2026 Approved JOSH MEISTER
Interior/Exterior Lathing 5/21/2026 Approved JOSH MEISTER
Shower Pan 5/21/2026 Approved JOSH MEISTER