7820 S TOLAND AVE 90045

Certificate Information: 7820 S TOLAND AVE 90045

Application / Permit
24014-10000-03317
Plan Check / Job No.
B24LA15267
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) 406 S.F GARAGE CONVERSION TO AN ADU WITH A (N) 144 S.F. ADDITION
Permit Issued
Issued on 1/22/2025
Issuing Office
Current Status
CofO Issued on 7/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2024 APPLICANT
Assigned to Plan Check Engineer 7/30/2024 JOSEPH RAFOLS
Corrections Issued 7/30/2024 JOSEPH RAFOLS
Applicant returned to address corrections 8/23/2024 JOSEPH RAFOLS
Plan Check Approved 11/14/2024 JOSEPH RAFOLS
Plan Check Approved 1/22/2025 JOSEPH RAFOLS
Issued 1/22/2025 APPLICANT
CofO in Progress 6/25/2025 RUBEN RIVAS
Permit Finaled 7/7/2025 RICHARD STEINBACH
Permit Finaled 7/7/2025 RICHARD STEINBACH
CofO Issued 7/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/21/2024 DARIN LAM
Roof/Waste drainage to street Cleared 8/21/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 8/22/2024 DARIN LAM
Sewer availability Cleared 8/22/2024 DARIN LAM
Specific Plan Cleared 8/28/2024 RICHARD WOO
Grading Pre-Inspection Cleared 8/30/2024 VASIL MIHALEV
Construction near power lines Cleared 11/9/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/20/2025 Partial Approval BOBBY KEY
Deputy Drilled-In Anchors 2/24/2025 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 2/25/2025 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Corrections Issued TEMISTOCLES CAAL
BUILDING-Rough-Frame 3/25/2025 Not Ready for Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 4/2/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 4/2/2025 Partial Approval JESUS PINEDA
PLUMBING-Rough 4/2/2025 Approved JESUS PINEDA
Special/Order Compliance 4/2/2025 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 4/8/2025 Approved JESUS PINEDA
HVAC-Rough 4/8/2025 Approved JESUS PINEDA
Insulation 4/11/2025 Approved HERBERT GIRON
Shower Pan 4/11/2025 Not Ready for Inspection HERBERT GIRON
Drywall Nailing 4/17/2025 Approved JAYLIN GRAVITTE
Shower Pan 4/18/2025 Corrections Issued JAYLIN GRAVITTE
Special/Order Compliance 4/18/2025 Partial Inspection HERBERT GIRON
Special/Order Compliance 4/18/2025 Partial Inspection TEMISTOCLES CAAL
Shower Pan 4/22/2025 Approved JAYLIN GRAVITTE
Underground Mechanical 4/23/2025 Partial Approval JESUS PINEDA
Interior/Exterior Lathing 4/30/2025 Approved TEMISTOCLES CAAL
Sewer 4/30/2025 Partial Approval TEMISTOCLES CAAL
Underground Mechanical 4/30/2025 Corrections Issued TEMISTOCLES CAAL
Underground Mechanical 5/2/2025 Partial Approval RUBEN RIVAS
Underground Mechanical 5/8/2025 Partial Approval JAYLIN GRAVITTE
ELECTRICAL-Final 5/21/2025 Corrections Issued KIRK SANDERS
HVAC-Final 5/21/2025 Corrections Issued KIRK SANDERS
Gas Test 5/28/2025 Approved JESUS PINEDA
Underground Mechanical 5/28/2025 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 6/18/2025 Approved MICHAEL ALLEN
Final 6/18/2025 Corrections Issued MICHAEL ALLEN
HVAC-Final 6/18/2025 Approved MICHAEL ALLEN
PLUMBING-Final 6/18/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/18/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 6/18/2025 Approved MICHAEL ALLEN
Underground Mechanical 6/18/2025 Approved MICHAEL ALLEN
Final 6/24/2025 OK to Issue CofO RUBEN RIVAS