17623 W BURBANK BLVD 91316

Certificate Information: 17623 W BURBANK BLVD 91316

Application / Permit
24014-10000-03313
Plan Check / Job No.
B24LA15241
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: Addition to single family dwelling, new kitchen and master bedroom, remodel 2 bathrooms.
Permit Issued
Issued on 9/16/2024
Issuing Office
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2024 APPLICANT
Assigned to Plan Check Engineer 8/2/2024 ALEXANDER JOO
Corrections Issued 8/5/2024 ALEXANDER JOO
Applicant returned to address corrections 8/27/2024 ALEXANDER JOO
Plan Check Approved 9/13/2024 ALEXANDER JOO
Issued 9/16/2024 APPLICANT
Permit Finaled 3/26/2026 JOHN JANSON
CofO Issued 3/26/2026 JOHN JANSON
Permit Finaled 3/26/2026 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/4/2024 LEE GUILBEAUX
Sewer availability Cleared 9/4/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/4/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/5/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Markarian,, Mardiros; Lic. No.: NA53434       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/27/2025 Partial Inspection MORRIS JACKSON
Deputy Drilled-In Anchors 2/25/2025 Conditional Approval MORRIS JACKSON
Wood Frame 2/25/2025 Partial Inspection MORRIS JACKSON
Footing/Foundation/Slab 3/3/2025 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 3/3/2025 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 3/21/2025 Partial Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Partial Approval MORRIS JACKSON
Footing/Foundation/Slab 4/29/2025 Approved MORRIS JACKSON
ELECTRICAL-Rough 5/6/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Partial Approval MORRIS JACKSON
HVAC-Rough 5/6/2025 Approved MORRIS JACKSON
PLUMBING-Rough 5/6/2025 Approved MORRIS JACKSON
BUILDING-Rough-Frame 5/27/2025 Approved MORRIS JACKSON
Green Building Rough 5/27/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 5/27/2025 Partial Approval MORRIS JACKSON
MERV13>=Rough 5/27/2025 Approved MORRIS JACKSON
Wood Frame 5/27/2025 Approved MORRIS JACKSON
Insulation 6/4/2025 Approved MORRIS JACKSON
Drywall Nailing 6/13/2025 Approved MORRIS JACKSON
Shower Pan 6/20/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 7/8/2025 Approved MORRIS JACKSON
Service/Power Release 8/22/2025 Approved MORRIS JACKSON
HVAC-Final 10/29/2025 Approved MORRIS JACKSON
ELECTRICAL-Final 11/3/2025 Approved MORRIS JACKSON
PLUMBING-Final 12/2/2025 Approved JEFFREY HARTLINE
Final 12/5/2025 Not Ready for Inspection MORRIS JACKSON
Green Building Final 12/5/2025 Approved MORRIS JACKSON
MERV13>=Final 12/5/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Approved MORRIS JACKSON
Smoke Detectors 12/5/2025 Approved MORRIS JACKSON
Final 1/5/2026 Partial Approval MORRIS JACKSON