6515 W 85TH ST 90045

Certificate Information: 6515 W 85TH ST 90045

Application / Permit
24014-10000-03295
Plan Check / Job No.
B24LA15139
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Conversion and addition to existing detached garage and storage in to an ADU per LAMC 12.22 A.33 (c)-(d). Design per licensed engineer.
Permit Issued
Issued on 12/16/2024
Issuing Office
Current Status
Issued on 12/16/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/26/2024 APPLICANT
Assigned to Plan Check Engineer 7/29/2024 CAROLEAN BASMA
Corrections Issued 7/29/2024 CAROLEAN BASMA
Applicant returned to address corrections 8/16/2024 CAROLEAN BASMA
Plan Check Approved 11/22/2024 CAROLEAN BASMA
Issued 12/16/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/10/2024 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 8/10/2024 LIAM ODONOVAN
Sewer availability Cleared 8/10/2024 LIAM ODONOVAN
Specific Plan Cleared 8/19/2024 RICHARD WOO
Eng Process Fee Ord 176,300 Cleared 8/22/2024 DIANA RENTERIA
Construction near power lines Cleared 11/19/2024 RIDWAN HARDY

Contact Information

Contractor Fehu Home Improvement Llc; Lic. No.: 1107500-B       ,
Engineer Santos,, Michael; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/20/2024 Conditional Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 12/20/2024 Approved MICHAEL ALLEN
Footing/Foundation/Slab 12/20/2024 Approved MICHAEL ALLEN
Underground Mechanical 12/20/2024 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Corrections Issued MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval MICHAEL ALLEN
Deputy Drilled-In Anchors 1/17/2025 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 1/21/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 1/21/2025 Corrections Issued ANTHONY EGSON
Green Building Rough 1/21/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 1/21/2025 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 1/21/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 1/21/2025 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 1/28/2025 Approved MICHAEL ALLEN
Gas Test 1/28/2025 Approved MICHAEL ALLEN
Green Building Rough 1/28/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 1/28/2025 Partial Approval MICHAEL ALLEN
Rough-Elec/Plmb/HVAC 1/28/2025 Approved MICHAEL ALLEN
Special/Order Compliance 1/28/2025 Conditional Approval MICHAEL ALLEN
Insulation 2/4/2025 Approved MICHAEL ALLEN
Drywall Nailing 2/10/2025 Approved EVAN COOPER
Shower Pan 2/24/2025 Approved JAYLIN GRAVITTE
PLUMBING-Final 3/19/2025 Corrections Issued RUBEN RIVAS
Sewer 3/19/2025 Approved RUBEN RIVAS
Final 4/3/2025 Not Ready for Inspection RUBEN RIVAS
Green Building Final 4/3/2025 Not Ready for Inspection RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Not Ready RUBEN RIVAS
Smoke Detectors 4/3/2025 Approved RUBEN RIVAS
Final 4/9/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Final 4/9/2025 Corrections Issued RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Not Required RUBEN RIVAS
Final 4/14/2025 Corrections Issued RUBEN RIVAS
Green Building Final 4/14/2025 Approved RUBEN RIVAS