4941 N NAGLE AVE 91423

Certificate Information: 4941 N NAGLE AVE 91423

Application / Permit
24014-10000-03293
Plan Check / Job No.
B24LA15136
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(ePLAN) Addition of 2nd story, attached garage, and trellis to existing 1-story single family dwelling to create a 2-story single family dwelling with attached garage. Work per engineer details.
Permit Issued
Issued on 3/21/2025
Issuing Office
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 VICTOR CHEN
Corrections Issued 8/5/2024 VICTOR CHEN
Quality Review Completed 8/14/2024 YOUNG KIM
Applicant returned to address corrections 10/15/2024 VICTOR CHEN
Applicant returned to address corrections 11/4/2024 VICTOR CHEN
Applicant returned to address corrections 11/19/2024 VICTOR CHEN
Plan Check Approved 11/25/2024 VICTOR CHEN
Plan Check Approved 1/9/2025 VICTOR CHEN
Plan Check Approved 3/11/2025 VICTOR CHEN
Issued 3/21/2025 APPLICANT
CofO in Progress 12/26/2025 MISAEL ESPARZA
Permit Finaled 12/31/2025 RUBEN SALAS
CofO Issued 12/31/2025 RUBEN SALAS
Permit Finaled 12/31/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/6/2024 BIAINA HARITUNIAN
ZI Cleared 8/6/2024 ASHLEY RODARTE
Eng Process Fee Ord 176,300 Cleared 8/12/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/12/2024 BIAINA HARITUNIAN
Hold Cleared 4/7/2025 ALEXIS SCHULTZ

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/1/2025 Partial Inspection MISAEL ESPARZA
Sewer 4/1/2025 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 4/3/2025 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 4/3/2025 Not Ready for Inspection MISAEL ESPARZA
Reinforced Masonry Frame 4/3/2025 Partial Inspection MISAEL ESPARZA
Footing/Foundation/Slab 4/10/2025 Approved MISAEL ESPARZA
Deputy Steel/Welding 4/18/2025 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Conditional Approval CHRISTOPHE COCHRAN
Deputy Wood Construction 5/16/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 5/19/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 5/19/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 5/19/2025 Approved MISAEL ESPARZA
Shower Pan 5/22/2025 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 5/22/2025 Corrections Issued MISAEL ESPARZA
HVAC-Rough 5/23/2025 Approved MISAEL ESPARZA
Shower Pan 5/23/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/28/2025 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 5/29/2025 Approved JACK KARGODORIAN
Green Building Rough 5/29/2025 Approved JACK KARGODORIAN
Insulation 6/9/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 6/9/2025 Approved MISAEL ESPARZA
Insulation 6/10/2025 Approved MISAEL ESPARZA
Drywall Nailing 6/13/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 12/11/2025 Corrections Issued MISAEL ESPARZA
HVAC-Final 12/11/2025 Approved MISAEL ESPARZA
PLUMBING-Final 12/11/2025 Corrections Issued MISAEL ESPARZA
Final 12/22/2025 OK to Issue CofO MISAEL ESPARZA
Green Building Final 12/22/2025 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 12/22/2025 SGSOV Approved MISAEL ESPARZA
Service/Power Release 12/22/2025 Approved MISAEL ESPARZA
Smoke Detectors 12/22/2025 Approved MISAEL ESPARZA