4941 N NAGLE AVE 91423
Certificate Information: 4941 N NAGLE AVE 91423
- Application / Permit
- 24014-10000-03293
- Plan Check / Job No.
- B24LA15136
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (ePLAN) Addition of 2nd story, attached garage, and trellis to existing 1-story single family dwelling to create a 2-story single family dwelling with attached garage. Work per engineer details.
- Permit Issued
- Issued on 3/21/2025
- Issuing Office
- Current Status
- CofO Issued on 12/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | VICTOR CHEN |
| Corrections Issued | 8/5/2024 | VICTOR CHEN |
| Quality Review Completed | 8/14/2024 | YOUNG KIM |
| Applicant returned to address corrections | 10/15/2024 | VICTOR CHEN |
| Applicant returned to address corrections | 11/4/2024 | VICTOR CHEN |
| Applicant returned to address corrections | 11/19/2024 | VICTOR CHEN |
| Plan Check Approved | 11/25/2024 | VICTOR CHEN |
| Plan Check Approved | 1/9/2025 | VICTOR CHEN |
| Plan Check Approved | 3/11/2025 | VICTOR CHEN |
| Issued | 3/21/2025 | APPLICANT |
| CofO in Progress | 12/26/2025 | MISAEL ESPARZA |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
| CofO Issued | 12/31/2025 | RUBEN SALAS |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/6/2024 | BIAINA HARITUNIAN |
| ZI | Cleared | 8/6/2024 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/12/2024 | BIAINA HARITUNIAN |
| Hold | Cleared | 4/7/2025 | ALEXIS SCHULTZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/1/2025 | Partial Inspection | MISAEL ESPARZA |
| Sewer | 4/1/2025 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Reinforced Masonry Frame | 4/3/2025 | Partial Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/10/2025 | Approved | MISAEL ESPARZA |
| Deputy Steel/Welding | 4/18/2025 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Conditional Approval | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 5/16/2025 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 5/19/2025 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 5/19/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 5/19/2025 | Approved | MISAEL ESPARZA |
| Shower Pan | 5/22/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 5/22/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 5/23/2025 | Approved | MISAEL ESPARZA |
| Shower Pan | 5/23/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/28/2025 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/29/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 5/29/2025 | Approved | JACK KARGODORIAN |
| Insulation | 6/9/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 6/9/2025 | Approved | MISAEL ESPARZA |
| Insulation | 6/10/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 6/13/2025 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Final | 12/11/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 12/11/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 12/11/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 12/22/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 12/22/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/22/2025 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 12/22/2025 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 12/22/2025 | Approved | MISAEL ESPARZA |