1622 N BENTON WAY 90026

Certificate Information: 1622 N BENTON WAY 90026

Application / Permit
24014-10000-03292
Plan Check / Job No.
B24LA15135
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. ADDITION (335 SF) AT THE REAR AND REMODEL OF EXISTING SFD. NEW REAR DECK. WORK PER ENGR DESIGN.
Permit Issued
Issued on 5/19/2025
Issuing Office
Current Status
Issued on 5/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/26/2024 APPLICANT
Assigned to Plan Check Engineer 7/30/2024 NEHEMIAS RAMOS
Corrections Issued 7/30/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 8/23/2024 NGHI SU
Applicant returned to address corrections 11/20/2024 NGHI SU
Plan Check Approved 11/22/2024 NGHI SU
Issued 5/19/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/6/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/7/2024 JEANIE LAM
Grading Pre-Inspection Cleared 8/25/2024 MICHAEL TEMPLE
Hydrant and Access approval Cleared 11/18/2024 PATRICK PEREZ

Contact Information

Architect Kim,, Peter Sung Taek; Lic. No.: C29012 984 NORDICA DRIVE      LOS ANGELES, CA 90026
Architect Kim,, Peter Sung Taek; Lic. No.: NA29012       ,
Contractor Malkoe Design & Construction; Lic. No.: 895875-B       ,
Contractor Malkoe Design Llc; Lic. No.: 895875-B       ,
Engineer Kwon,, Ohsung; Lic. No.: NA85429       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/26/2025 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2025 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 10/15/2025 Conditional Approval DEVON JACKSON
BUILDING-Rough-Frame 10/27/2025 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/27/2025 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 10/27/2025 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/27/2025 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 10/27/2025 Partial Approval HAMIK HARTOUNIAN
Insulation 11/6/2025 Partial Approval GEM DE OCAMPO
Drywall Nailing 11/14/2025 Partial Approval ALEX COLIN
BUILDING-Rough-Frame 12/11/2025 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/11/2025 Approved HAMIK HARTOUNIAN
Green Building Rough 12/11/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 12/11/2025 Corrections Issued HAMIK HARTOUNIAN
Insulation 12/16/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 12/16/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 12/16/2025 Approved FREDDIE RIVERA
Shower Pan 12/16/2025 Approved FREDDIE RIVERA
Drywall Nailing 12/22/2025 Approved GEM DE OCAMPO
Deck 1/14/2026 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/16/2026 Approved FREDDIE RIVERA
Final 4/16/2026 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 4/16/2026 Approved FREDDIE RIVERA
Green Building Final 4/16/2026 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 4/16/2026 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 4/16/2026 Partial Inspection FREDDIE RIVERA
Final 5/18/2026 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/18/2026 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 5/18/2026 Approved HAMIK HARTOUNIAN