1622 N BENTON WAY 90026
Certificate Information: 1622 N BENTON WAY 90026
- Application / Permit
- 24014-10000-03292
- Plan Check / Job No.
- B24LA15135
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. ADDITION (335 SF) AT THE REAR AND REMODEL OF EXISTING SFD. NEW REAR DECK. WORK PER ENGR DESIGN.
- Permit Issued
- Issued on 5/19/2025
- Issuing Office
- Current Status
- Issued on 5/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 7/30/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 8/23/2024 | NGHI SU |
| Applicant returned to address corrections | 11/20/2024 | NGHI SU |
| Plan Check Approved | 11/22/2024 | NGHI SU |
| Issued | 5/19/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/6/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2024 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 8/25/2024 | MICHAEL TEMPLE |
| Hydrant and Access approval | Cleared | 11/18/2024 | PATRICK PEREZ |
Contact Information
| Architect | Kim,, Peter Sung Taek; Lic. No.: C29012 | 984 NORDICA DRIVE LOS ANGELES, CA 90026 |
| Architect | Kim,, Peter Sung Taek; Lic. No.: NA29012 | , |
| Contractor | Malkoe Design & Construction; Lic. No.: 895875-B | , |
| Contractor | Malkoe Design Llc; Lic. No.: 895875-B | , |
| Engineer | Kwon,, Ohsung; Lic. No.: NA85429 | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/26/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 10/15/2025 | Conditional Approval | DEVON JACKSON |
| BUILDING-Rough-Frame | 10/27/2025 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/27/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 10/27/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/27/2025 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 10/27/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 11/6/2025 | Partial Approval | GEM DE OCAMPO |
| Drywall Nailing | 11/14/2025 | Partial Approval | ALEX COLIN |
| BUILDING-Rough-Frame | 12/11/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/11/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 12/11/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/11/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Insulation | 12/16/2025 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 12/16/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 12/16/2025 | Approved | FREDDIE RIVERA |
| Shower Pan | 12/16/2025 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 12/22/2025 | Approved | GEM DE OCAMPO |
| Deck | 1/14/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/16/2026 | Approved | FREDDIE RIVERA |
| Final | 4/16/2026 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/16/2026 | Approved | FREDDIE RIVERA |
| Green Building Final | 4/16/2026 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 4/16/2026 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 4/16/2026 | Partial Inspection | FREDDIE RIVERA |
| Final | 5/18/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/18/2026 | Approved | HAMIK HARTOUNIAN |