ePlan: Addition to (E) Single Family Dwelling. Work per Engineered design.
Permit Issued
Issued on 9/26/2024
Issuing Office
Current Status
CofO Issued on 5/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2024 APPLICANT
Assigned to Plan Check Engineer 8/2/2024 AMY GUEVARRA
Corrections Issued 8/7/2024 AMY GUEVARRA
Applicant returned to address corrections 9/11/2024 AMY GUEVARRA
Plan Check Approved 9/24/2024 AMY GUEVARRA
Issued 9/26/2024 APPLICANT
CofO in Progress 5/21/2026 JOSH MEISTER
CofO Issued 5/22/2026 DEROLD HAUFF
Permit Finaled 5/22/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/10/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 9/10/2024 CELINA MORENO
Sewer availability Cleared 9/10/2024 CELINA MORENO

Contact Information

Architect Strumwasser,, Scott Mark; Lic. No.: C21151 5971 W THIRD STREET      LOS ANGELES, CA 90036
Contractor Owner-Builder       ,
Engineer Vinci,, James Richard; Lic. No.: S4411 175 E WILBUR ROAD STE 103      THOUSAND OAKS, CA 91360

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/4/2025 Conditional Approval JOSE MACIAS
Footing/Foundation/Slab 4/8/2025 Approved JOSE MACIAS
METHANE-Barrier 4/8/2025 Approved JOSE MACIAS
METHANE-Subgrade 4/8/2025 Approved JOSE MACIAS
Insulation 4/18/2025 Partial Inspection JOSE MACIAS
Deputy Wood Construction 4/24/2025 Conditional Approval JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Approved ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Corrections Issued JOSE MACIAS
Deputy Wood Construction 7/17/2025 Conditional Approval JOSH MEISTER
ELECTRICAL-Rough 7/29/2025 Corrections Issued JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Approved JOSE MACIAS
Gas Test 7/29/2025 Not Ready for Inspection JOSE MACIAS
HVAC-Rough 7/29/2025 Not Ready for Inspection JOSE MACIAS
PLUMBING-Rough 7/29/2025 Approved JOSE MACIAS
Wood Frame 7/29/2025 Approved JOSE MACIAS
ELECTRICAL-Rough 8/5/2025 Corrections Issued JOSE MACIAS
HVAC-Rough 8/5/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 8/15/2025 Not Ready for Inspection JOSE MACIAS
Interior/Exterior Lathing 8/15/2025 Approved JOSE MACIAS
ELECTRICAL-Rough 8/19/2025 Approved JOSE MACIAS
Insulation 8/22/2025 Approved OSVALDO PARAMO
Drywall Nailing 9/9/2025 Approved JOSE MACIAS
HVAC-Rough 9/9/2025 Approved JOSE MACIAS
Interior/Exterior Lathing 9/16/2025 Approved JOSE MACIAS
Shower Pan 9/16/2025 Approved JOSE MACIAS
BUILDING-Rough-Frame 3/10/2026 Approved ALIZAH MAYAGOITIA
Final 3/10/2026 Corrections Issued ALIZAH MAYAGOITIA
METHANE-Final 3/10/2026 Approved ALIZAH MAYAGOITIA
METHANE-Rough 3/10/2026 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 3/10/2026 Approved ALIZAH MAYAGOITIA
Final 4/28/2026 Not Ready for Inspection JOSH MEISTER
Final 5/6/2026 Not Ready for Inspection JOSH MEISTER
Final 5/20/2026 OK to Issue CofO JOSH MEISTER