5410 S 10TH AVE 90043
Certificate Information: 5410 S 10TH AVE 90043
- Application / Permit
- 24014-10000-03267
- Plan Check / Job No.
- B24LA14912
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - CONVERT EXISTING REC ROOM AND PORTION OF GARAGE AND ADDITION TO 2 STORY ADU WITH ATTACHED GARAGE PER 12.22 A33 C & D
- Permit Issued
- Issued on 4/23/2025
- Issuing Office
- Current Status
- Issued on 4/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2024 | STARR CHEN |
| Corrections Issued | 11/12/2024 | STARR CHEN |
| Quality Review Completed | 11/13/2024 | EUGENE BARBEAU |
| Plan Check Approved | 2/28/2025 | STARR CHEN |
| Issued | 4/23/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 11/14/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 2/4/2025 | JESSICA OPINION |
| Hydrant and Access approval | Cleared | 2/20/2025 | FRANK GOMEZ |
| Hold | Cleared | 5/7/2025 | MARIA VENDIVIL |
Contact Information
| Contractor | Goliath Construction; Lic. No.: 1056541-B | , |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/9/2025 | Partial Approval | LUIS CASTRO |
| Footing/Foundation/Slab | 5/9/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 5/9/2025 | Partial Approval | LUIS CASTRO |
| Deputy Drilled-In Anchors | 5/14/2025 | Conditional Approval | ANTHONY RAMOS |
| Excavation/Setback/Form/Re-Bar | 5/15/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 5/15/2025 | Approved | LUIS CASTRO |
| Deputy Wood Construction | 5/28/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Partial Approval | LUIS CASTRO |
| Deputy Wood Construction | 6/3/2025 | Conditional Approval | ANTHONY RAMOS |
| ELECTRICAL-Rough | 6/26/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 6/26/2025 | Approved | LUIS CASTRO |
| Sewer | 6/26/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 6/27/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 7/8/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 7/8/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 7/8/2025 | Approved | LUIS CASTRO |
| Insulation | 7/11/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 7/23/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 7/29/2025 | Approved | RONNIE MEDINA |
| Shower Pan | 7/29/2025 | Approved | RONNIE MEDINA |
| ELECTRICAL-Final | 4/2/2026 | Corrections Issued | LUIS CASTRO |
| Final | 4/2/2026 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 4/2/2026 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Final | 4/2/2026 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 4/2/2026 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Not Required | LUIS CASTRO |
| Smoke Detectors | 4/2/2026 | Approved | LUIS CASTRO |
| Special/Order Compliance | 4/2/2026 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Final | 4/6/2026 | Approved | LUIS CASTRO |
| Final | 4/6/2026 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 4/6/2026 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Final | 4/6/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/6/2026 | Approved | LUIS CASTRO |
| Underground Mechanical | 4/6/2026 | Approved | LUIS CASTRO |
| Final | 4/16/2026 | Partial Approval | LUIS CASTRO |
| Green Building Final | 4/16/2026 | Approved | LUIS CASTRO |