4048 1/2 N SOMERS AVE 90065
Certificate Information: 4048 1/2 N SOMERS AVE 90065
- Application / Permit
- 24014-10000-03250
- Plan Check / Job No.
- B24LA14716
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: New 1-Story Detached ADU per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/18/2025
- Issuing Office
- Current Status
- CofO Issued on 9/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2024 | SERGIO MUNIZ |
| Corrections Issued | 8/3/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/3/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 10/30/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 12/13/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 12/19/2024 | DAVID CASTILLO |
| Plan Check Approved | 12/24/2024 | DAVID CASTILLO |
| Issued | 1/18/2025 | APPLICANT |
| CofO in Progress | 9/17/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 9/18/2025 | DEROLD HAUFF |
| Permit Finaled | 9/18/2025 | DEROLD HAUFF |
| CofO Issued | 9/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/12/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 9/12/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 9/12/2024 | DAVID LOPEZ |
| Grading Pre-Inspection | Cleared | 9/12/2024 | MICHAEL TEMPLE |
| Supp. Use District POD/CDO/TDO | Cleared | 10/1/2024 | ANDREA MAGANA-WITHERS |
| GPI Written Notices | Cleared | 12/12/2024 | SERGIO MUNIZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/24/2025 | Partial Approval | NICHOLAS LOPEZ |
| Underground Mechanical | 3/24/2025 | Partial Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 3/26/2025 | Approved | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 4/2/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Partial Approval | NICHOLAS LOPEZ |
| Deputy Wood Construction | 4/16/2025 | Conditional Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 5/8/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 5/8/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 5/8/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Rough | 5/8/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 5/8/2025 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 5/8/2025 | Approved | NICHOLAS LOPEZ |
| Verify Sprinkler Sign Off | 5/8/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 5/14/2025 | Partial Approval | NICHOLAS LOPEZ |
| Insulation | 6/3/2025 | Partial Approval | REGINA MENDEZ |
| Drywall Nailing | 6/9/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 6/24/2025 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 9/10/2025 | Approved | NICHOLAS LOPEZ |
| Final | 9/10/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 9/10/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 9/10/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/10/2025 | SGSOV No Gas | NICHOLAS LOPEZ |
| Service/Power Release | 9/10/2025 | Not Required | NICHOLAS LOPEZ |
| Smoke Detectors | 9/10/2025 | Approved | NICHOLAS LOPEZ |
| Final | 9/16/2025 | OK to Issue CofO | NICHOLAS LOPEZ |