2440 S COLBY AVE 90064
Certificate Information: 2440 S COLBY AVE 90064
- Application / Permit
- 24014-10000-03240
- Plan Check / Job No.
- B24LA14663
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: NEW 22'9" x 17'5" ADDITION AND 17'9" x 10' DECK ADDITION TO (E) SFD. INTERIOR REMODEL OF (E) SFD.
- Permit Issued
- Issued on 9/6/2024
- Issuing Office
- Current Status
- Issued on 9/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2024 | ISIS ARGUETA |
| Corrections Issued | 7/27/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 8/29/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 9/3/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 9/5/2024 | MIROOSH KHACHATOORIAN |
| Issued | 9/6/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 8/6/2024 | DARIN LAM |
| Specific Plan | Cleared | 8/28/2024 | KYLE WINSTON |
| Specific Plan | Cleared | 8/28/2024 | RICHARD WOO |
Contact Information
| Architect | Woodcraft,, Lawrence Albert; Lic. No.: NA23651 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/19/2024 | Approved | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 10/16/2024 | Approved | JOHN MATTILLO |
| BUILDING-Rough-Frame | 10/24/2024 | Partial Approval | RYAN BARNES |
| Green Building Rough | 10/24/2024 | Partial Approval | RYAN BARNES |
| MERV13>=Rough | 10/24/2024 | Approved | RYAN BARNES |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Partial Approval | RYAN BARNES |
| Insulation | 10/29/2024 | Partial Approval | RYAN BARNES |
| Pre-Inspection | 10/29/2024 | Not Ready for Inspection | RYAN BARNES |
| BUILDING-Rough-Frame | 11/26/2024 | Conditional Approval | RYAN BARNES |
| ELECTRICAL-Rough | 11/26/2024 | Partial Approval | RYAN BARNES |
| Green Building Rough | 11/26/2024 | Approved | RYAN BARNES |
| PLUMBING-Rough | 11/26/2024 | Partial Approval | RYAN BARNES |
| Insulation | 12/4/2024 | No Access for Inspection | RYAN BARNES |
| ELECTRICAL-Rough | 12/6/2024 | Approved | RYAN BARNES |
| Insulation | 12/6/2024 | Approved | RYAN BARNES |
| PLUMBING-Rough | 12/6/2024 | Approved | RYAN BARNES |
| Wood Frame | 12/6/2024 | Approved | RYAN BARNES |
| Drywall Nailing | 12/11/2024 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 2/3/2025 | Order to Comply Issued | RYAN BARNES |
| PLUMBING-Rough | 2/3/2025 | Partial Approval | RYAN BARNES |
| Shower Pan | 2/10/2025 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 2/18/2025 | Partial Approval | RYAN BARNES |
| ELECTRICAL-Rough | 3/10/2025 | Partial Approval | RYAN BARNES |
| PLUMBING-Rough | 3/10/2025 | Partial Approval | RYAN BARNES |
| HVAC-Final | 7/10/2025 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 10/7/2025 | SGSOV Not Ready | RYAN BARNES |
| Pre-Inspection | 10/10/2025 | Not Ready for Inspection | RYAN BARNES |
| BUILDING-Rough-Frame | 10/20/2025 | Approved | RYAN BARNES |
| Final | 10/20/2025 | Conditional Approval | RYAN BARNES |
| Footing/Foundation/Slab | 10/20/2025 | Approved | RYAN BARNES |
| Green Building Final | 10/20/2025 | Approved | RYAN BARNES |
| MERV13>=Final | 10/20/2025 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 10/20/2025 | Approved | RYAN BARNES |