842 S MULLEN AVE 90005
Certificate Information: 842 S MULLEN AVE 90005
- Application / Permit
- 24014-10000-03223
- Plan Check / Job No.
- B24LA14506
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **Eplan.** Remove majority of (E) SFD including rear deck and trellis. New 2nd story add., new deck/trellis add., and int./ext. remodel. < NFPA 13D Fire sprinklers REQd Thru-out BLDG>.
- Permit Issued
- Issued on 1/1/2025
- Issuing Office
- Current Status
- CofO Issued on 3/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | HUAN LE |
| Corrections Issued | 9/13/2024 | HUAN LE |
| Quality Review Completed | 10/4/2024 | JOHN FRANCIA |
| Applicant returned to address corrections | 12/18/2024 | HUAN LE |
| Plan Check Approved | 12/31/2024 | HUAN LE |
| Issued | 1/1/2025 | APPLICANT |
| CofO in Progress | 3/16/2026 | JOSH MEISTER |
| Permit Finaled | 3/19/2026 | DEROLD HAUFF |
| CofO Issued | 3/19/2026 | DEROLD HAUFF |
| Permit Finaled | 3/19/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/25/2024 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2024 | ABEL CASILLAS |
| Sewer availability | Cleared | 11/16/2024 | ABEL CASILLAS |
| Disturb/Remove Protected Trees | Cleared | 11/18/2024 | RICHARD SANCHEZ |
Contact Information
| Architect | Musolino,, John Michael; Lic. No.: NA33574 | , |
| Contractor | Owner-Builder | , |
| Engineer | Van, Elden, Alexander; Lic. No.: NA71696 | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/5/2025 | Conditional Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Partial Approval | RONNIE MINDANAO |
| PLUMBING-Rough | 4/11/2025 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Partial Approval | JEFFREY MEAD |
| Insulation | 4/15/2025 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Deputy Wood Construction | 6/3/2025 | Conditional Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2025 | Conditional Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 6/10/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 6/12/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 6/12/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 6/16/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 6/16/2025 | Approved | JEFFREY MEAD |
| Shower Pan | 6/16/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 6/24/2025 | Approved | WILLIAM SIERRA |
| Insulation | 6/24/2025 | Partial Approval | WILLIAM SIERRA |
| Interior/Exterior Lathing | 6/24/2025 | Approved | WILLIAM SIERRA |
| Green Building Rough | 6/26/2025 | Approved | JOSE MACIAS |
| Insulation | 6/26/2025 | Approved | JOSE MACIAS |
| Wood Frame | 6/26/2025 | Approved | JOSE MACIAS |
| Drywall Nailing | 7/2/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 7/2/2025 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 10/20/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 10/20/2025 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 10/20/2025 | Corrections Issued | JEFFREY MEAD |
| Smoke Detectors | 10/20/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/27/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 10/27/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 10/27/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 10/27/2025 | Partial Inspection | JEFFREY MEAD |
| Green Building Final | 10/27/2025 | Approved | JEFFREY MEAD |
| HVAC-Final | 10/27/2025 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Final | 10/27/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 10/27/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 10/27/2025 | SGSOV Not Ready | JEFFREY MEAD |
| Final | 11/10/2025 | Partial Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 11/10/2025 | Approved | JEFFREY MEAD |
| METHANE-Barrier | 11/10/2025 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 11/10/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 11/21/2025 | Approved | JEFFREY MEAD |
| Final | 11/21/2025 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Final | 11/21/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 11/21/2025 | Approved | JEFFREY MEAD |
| Final | 3/16/2026 | OK to Issue CofO | JOSH MEISTER |