3815 S 2ND AVE 90008
Certificate Information: 3815 S 2ND AVE 90008
- Application / Permit
- 24014-10000-03211
- Plan Check / Job No.
- B24LA14417
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE WITH ADDITION TO NEW ADU PER ORDINANCE
- Permit Issued
- Issued on 12/16/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | ADAM HEGAZI |
| Corrections Issued | 7/26/2024 | ADAM HEGAZI |
| Building Plans Picked Up | 8/5/2024 | APPLICANT |
| Applicant returned to address corrections | 10/21/2024 | MINA HABILI |
| Plan Check Approved | 12/16/2024 | EDWIN MARTINEZ |
| Issued | 12/16/2024 | APPLICANT |
| CofO in Progress | 3/18/2026 | LUIS CASTRO |
| No Progress | 3/18/2026 | MICHAEL LEWIS |
| CofO in Progress | 3/18/2026 | MICHAEL LEWIS |
| Permit Finaled | 3/19/2026 | DEROLD HAUFF |
| CofO Issued | 3/19/2026 | DEROLD HAUFF |
| Permit Finaled | 3/19/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 8/6/2024 | JUSTIN BICOL |
| Tenant Habitability Plan | Cleared | 8/9/2024 | RICARDO BOHORQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 8/14/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 11/14/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Brunmier,, David Wayne; Lic. No.: C80545 | 18567 VALLEY BLVD. BLOOMINGTON, CA 92316 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/3/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 4/11/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 4/11/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 6/18/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 6/30/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 6/30/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 6/30/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 7/2/2025 | Corrections Issued | LUIS CASTRO |
| Interior/Exterior Lathing | 7/2/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 8/1/2025 | Approved | DEVON JACKSON |
| Shower Pan | 8/1/2025 | Approved | DEVON JACKSON |
| Drywall Nailing | 8/12/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 8/12/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 1/27/2026 | Approved | LUIS CASTRO |
| Final | 1/27/2026 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 1/27/2026 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Rough | 1/27/2026 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Not Ready | LUIS CASTRO |
| Smoke Detectors | 1/27/2026 | Approved | LUIS CASTRO |
| Final | 2/18/2026 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 2/18/2026 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Not Ready | LUIS CASTRO |
| Insulation | 2/24/2026 | No Access for Inspection | MICHAEL LEWIS |
| Final | 3/12/2026 | Corrections Issued | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Approved | LUIS CASTRO |
| ELECTRICAL-Final | 3/17/2026 | Approved | LUIS CASTRO |
| Final | 3/17/2026 | OK to Issue CofO | LUIS CASTRO |
| HVAC-Final | 3/17/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 3/17/2026 | Approved | LUIS CASTRO |