2765 N CASIANO ROAD 90077
Certificate Information: 2765 N CASIANO ROAD 90077
- Application / Permit
- 24014-10000-03208
- Plan Check / Job No.
- B24LA14398
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND INTERIOR AND EXTERIOR REMODEL TO (E) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 2/21/2025
- Issuing Office
- Current Status
- CofO Issued on 5/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | DANIEL YIP |
| Corrections Issued | 8/13/2024 | DANIEL YIP |
| Quality Review Completed | 8/14/2024 | GARO TELMI |
| Applicant returned to address corrections | 1/15/2025 | DANIEL YIP |
| Plan Check Approved | 1/27/2025 | DANIEL YIP |
| Issued | 2/21/2025 | APPLICANT |
| CofO in Progress | 5/14/2026 | RYAN SALAZAR |
| Permit Finaled | 5/14/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/14/2026 | RICHARD STEINBACH |
| CofO Issued | 5/14/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hold | Cleared | 8/7/2024 | TERESA RIVAS |
| Grading Pre-Inspection | Cleared | 8/20/2024 | VASIL MIHALEV |
| Roof/Waste drainage to street | Cleared | 10/25/2024 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2024 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 10/28/2024 | TIFFANY CORRALES |
Contact Information
| Contractor | Eco Renovate Pros; Lic. No.: 1054754-B | , |
| Contractor | Riga Builders Inc; Lic. No.: 1054754-B | , |
| Engineer | Barragan,, Pedro; Lic. No.: C90531 | 329 N HUBBARD AVE SAN FERNANDO, CA 91340 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/9/2025 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 4/17/2025 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Partial Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 7/1/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/18/2025 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/4/2025 | No Access for Inspection | CARLOS MATAMOROS |
| Rough-Elec/Plmb/HVAC | 8/4/2025 | No Access for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/6/2025 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 8/6/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/6/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/19/2025 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 8/19/2025 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 8/20/2025 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/4/2025 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 9/4/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/4/2025 | Corrections Issued | CARLOS MATAMOROS |
| Insulation | 9/26/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/26/2025 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 10/10/2025 | Approved | CARLOS MATAMOROS |
| Gas Test | 2/10/2026 | Corrections Issued | EVAN COOPER |
| Final | 5/7/2026 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 5/7/2026 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/7/2026 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 5/7/2026 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 5/13/2026 | Conditional Approval | ANDREW NAVE |
| Final | 5/14/2026 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 5/14/2026 | Approved | RYAN SALAZAR |