3934 1/2 S 3RD AVE 90008
Certificate Information: 3934 1/2 S 3RD AVE 90008
- Application / Permit
- 24014-10000-03200
- Plan Check / Job No.
- B24LA14344
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED GARAGE CONVERSION TO ADU WITH ADDITION PER ORDINANCE WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/25/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | MINA HABILI |
| Corrections Issued | 7/28/2024 | MINA HABILI |
| Building Plans Picked Up | 8/5/2024 | APPLICANT |
| Applicant returned to address corrections | 11/22/2024 | DANIEL SMILEY |
| Plan Check Approved | 11/25/2024 | NEHEMIAS RAMOS |
| Issued | 11/25/2024 | APPLICANT |
| CofO in Progress | 7/15/2025 | LUIS CASTRO |
| Permit Finaled | 7/16/2025 | DEROLD HAUFF |
| CofO Issued | 7/16/2025 | DEROLD HAUFF |
| Permit Finaled | 7/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 8/29/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2024 | JEANIE LAM |
| Sewer availability | Cleared | 9/9/2024 | JEANIE LAM |
| Construction near power lines | Cleared | 11/19/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/13/2024 | Not Ready for Inspection | BARRY HACHE |
| Underground Mechanical | 12/13/2024 | Corrections Issued | BARRY HACHE |
| Underground Mechanical | 12/17/2024 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 12/24/2024 | Corrections Issued | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 1/17/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 1/22/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 1/22/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 1/22/2025 | Approved | LUIS CASTRO |
| Sewer | 1/22/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 1/24/2025 | Partial Approval | LUIS CASTRO |
| Sewer | 1/24/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 2/21/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 2/21/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 2/25/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Rough | 2/27/2025 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 2/28/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 2/28/2025 | Approved | LUIS CASTRO |
| Insulation | 3/4/2025 | Not Ready for Inspection | LUIS CASTRO |
| Interior/Exterior Lathing | 3/10/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 3/11/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 3/13/2025 | Partial Approval | LUIS CASTRO |
| Drywall Nailing | 3/20/2025 | Approved | LUIS CASTRO |
| Shower Pan | 4/9/2025 | Corrections Issued | ALEX COLIN |
| Shower Pan | 4/14/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 5/16/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 6/17/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 6/17/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 6/17/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 6/26/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 6/26/2025 | Approved | LUIS CASTRO |
| Final | 6/26/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 6/26/2025 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Rough | 6/26/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 6/26/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 6/26/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 6/30/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 6/30/2025 | Approved | LUIS CASTRO |
| Final | 7/9/2025 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Final | 7/9/2025 | Approved | LUIS CASTRO |
| Final | 7/15/2025 | OK to Issue CofO | LUIS CASTRO |