3934 1/2 S 3RD AVE 90008

Certificate Information: 3934 1/2 S 3RD AVE 90008

Application / Permit
24014-10000-03200
Plan Check / Job No.
B24LA14344
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED GARAGE CONVERSION TO ADU WITH ADDITION PER ORDINANCE WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 11/25/2024
Issuing Office
Metro
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 MINA HABILI
Corrections Issued 7/28/2024 MINA HABILI
Building Plans Picked Up 8/5/2024 APPLICANT
Applicant returned to address corrections 11/22/2024 DANIEL SMILEY
Plan Check Approved 11/25/2024 NEHEMIAS RAMOS
Issued 11/25/2024 APPLICANT
CofO in Progress 7/15/2025 LUIS CASTRO
Permit Finaled 7/16/2025 DEROLD HAUFF
CofO Issued 7/16/2025 DEROLD HAUFF
Permit Finaled 7/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/29/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 8/29/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/9/2024 JEANIE LAM
Sewer availability Cleared 9/9/2024 JEANIE LAM
Construction near power lines Cleared 11/19/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/13/2024 Not Ready for Inspection BARRY HACHE
Underground Mechanical 12/13/2024 Corrections Issued BARRY HACHE
Underground Mechanical 12/17/2024 Partial Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 12/24/2024 Corrections Issued LUIS CASTRO
Excavation/Setback/Form/Re-Bar 1/17/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 1/22/2025 Partial Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 1/22/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 1/22/2025 Approved LUIS CASTRO
Sewer 1/22/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 1/24/2025 Partial Approval LUIS CASTRO
Sewer 1/24/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 2/21/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 2/21/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Approved LUIS CASTRO
HVAC-Rough 2/25/2025 Corrections Issued LUIS CASTRO
HVAC-Rough 2/27/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 2/28/2025 Partial Approval LUIS CASTRO
HVAC-Rough 2/28/2025 Approved LUIS CASTRO
Insulation 3/4/2025 Not Ready for Inspection LUIS CASTRO
Interior/Exterior Lathing 3/10/2025 Partial Approval LUIS CASTRO
Insulation 3/11/2025 Approved LUIS CASTRO
Drywall Nailing 3/13/2025 Partial Approval LUIS CASTRO
Drywall Nailing 3/20/2025 Approved LUIS CASTRO
Shower Pan 4/9/2025 Corrections Issued ALEX COLIN
Shower Pan 4/14/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 5/16/2025 Approved LUIS CASTRO
ELECTRICAL-Final 6/17/2025 Corrections Issued LUIS CASTRO
HVAC-Final 6/17/2025 Corrections Issued LUIS CASTRO
PLUMBING-Final 6/17/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 6/26/2025 Approved LUIS CASTRO
ELECTRICAL-Final 6/26/2025 Approved LUIS CASTRO
Final 6/26/2025 Corrections Issued LUIS CASTRO
Green Building Final 6/26/2025 Not Ready for Inspection LUIS CASTRO
Green Building Rough 6/26/2025 Approved LUIS CASTRO
HVAC-Final 6/26/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 6/26/2025 Approved LUIS CASTRO
ELECTRICAL-Final 6/30/2025 Approved LUIS CASTRO
HVAC-Final 6/30/2025 Approved LUIS CASTRO
Final 7/9/2025 Not Ready for Inspection LUIS CASTRO
Green Building Final 7/9/2025 Approved LUIS CASTRO
Final 7/15/2025 OK to Issue CofO LUIS CASTRO