3630 1/4 W SENECA AVE 90039
Certificate Information: 3630 1/4 W SENECA AVE 90039
- Application / Permit
- 24014-10000-03197
- Plan Check / Job No.
- B24LA14329
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO A DETACHED ACCESSORY DWELLING UNIT WITH ADDITION PER GC 66323(a)(2) ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/5/2025
- Issuing Office
- Metro
- Current Status
- Issued on 12/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | MINA HABILI |
| Corrections Issued | 7/27/2024 | MINA HABILI |
| Building Plans Picked Up | 8/5/2024 | APPLICANT |
| Applicant returned to address corrections | 2/21/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 4/10/2025 | NGHI SU |
| Plan Check Approved | 8/1/2025 | NEHEMIAS RAMOS |
| Issued | 12/5/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/5/2025 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 7/18/2025 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 8/1/2025 | JEREMY CHOK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 1/28/2026 | Partial Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 1/30/2026 | Partial Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 2/12/2026 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2026 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 3/13/2026 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 3/13/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 3/13/2026 | Approved | DAVID WILLIAMS |
| Insulation | 3/24/2026 | Corrections Issued | GEM DE OCAMPO |
| Interior/Exterior Lathing | 3/24/2026 | Partial Approval | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 4/1/2026 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/1/2026 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 4/1/2026 | Approved | GEM DE OCAMPO |
| Green Building Rough | 4/1/2026 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 4/2/2026 | Approved | NICHOLAS LOPEZ |
| Sewer | 4/30/2026 | Corrections Issued | GEM DE OCAMPO |
| Sewer | 5/4/2026 | Approved | NICHOLAS LOPEZ |