4658 E PAULA ST 90032

Certificate Information: 4658 E PAULA ST 90032

Application / Permit
24014-10000-03188
Plan Check / Job No.
B24LA14260
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: GARAGE CONVERSION TO ADU WITH ADDITION PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 8/12/2024
Issuing Office
Current Status
CofO Issued on 5/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2024 APPLICANT
Assigned to Plan Check Engineer 7/24/2024 MOHAMMAD ESMAILI
Corrections Issued 7/25/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 7/31/2024 GURUNATH NESARAJAH
Plan Check Approved 8/11/2024 GURUNATH NESARAJAH
Issued 8/12/2024 APPLICANT
CofO in Progress 5/23/2025 LILIANA PORTILLO
No Progress 5/23/2025 CHARLES BOGHOSKHAN
CofO in Progress 5/23/2025 CHARLES BOGHOSKHAN
Permit Finaled 5/29/2025 DEROLD HAUFF
CofO Issued 5/29/2025 DEROLD HAUFF
Permit Finaled 5/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/25/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/25/2024 DAVID LOPEZ
Grading Pre-Inspection Cleared 7/25/2024 MOHAMMAD ESMAILI
Roof/Waste drainage to street Cleared 7/25/2024 DAVID LOPEZ
Sewer availability Cleared 7/25/2024 DAVID LOPEZ

Contact Information

Contractor Maad Construction; Lic. No.: 1082474-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/14/2024 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 11/25/2024 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 12/24/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 12/24/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 1/16/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 1/16/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 1/16/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/6/2025 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/6/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 2/6/2025 Partial Approval LILIANA PORTILLO
Shower Pan 2/6/2025 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 2/6/2025 Approved LILIANA PORTILLO
Insulation 2/20/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 2/20/2025 Approved LILIANA PORTILLO
Drywall Nailing 3/3/2025 Approved JOSH MEISTER
BUILDING-Rough-Frame 4/9/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 4/9/2025 Not Ready for Inspection LILIANA PORTILLO
Final 4/9/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 4/9/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 4/9/2025 Approved LILIANA PORTILLO
HVAC-Final 4/9/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 4/9/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 4/9/2025 Not Ready for Inspection LILIANA PORTILLO
Final 5/15/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 5/15/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 5/15/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 5/22/2025 Approved LILIANA PORTILLO
Final 5/22/2025 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 5/22/2025 Approved LILIANA PORTILLO
PLUMBING-Final 5/22/2025 Approved LILIANA PORTILLO