16809 W OAK VIEW DR 91436

Certificate Information: 16809 W OAK VIEW DR 91436

Application / Permit
24014-10000-03167
Plan Check / Job No.
B24LA13898
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: New addition and remodeling to (E) 1st floor SFD + extend (E) balcony on 2nd floor
Permit Issued
Issued on 11/8/2024
Issuing Office
Current Status
Issued on 11/8/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/22/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 ARSALAN SHABESTARI
Corrections Issued 7/27/2024 ARSALAN SHABESTARI
Quality Review Completed 8/6/2024 YOUNG KIM
Plan Check Approved 11/5/2024 ARSALAN SHABESTARI
Plan Check Approved 11/6/2024 ARSALAN SHABESTARI
Issued 11/8/2024 APPLICANT

Permit Application Clearance Information

Tract Map conditions Cleared 8/9/2024 DANIEL CORONADO
ZA Case Cleared 8/9/2024 DANIEL CORONADO
Roof/Waste drainage to street Cleared 8/12/2024 BIAINA HARITUNIAN
Private sewage disp. approval Cleared 9/4/2024 MICHAEL TEMPLE
Eng Process Fee Ord 176,300 Cleared 10/10/2024 MARKOS PEREZ-BRAN
Grading Pre-Inspection Cleared 10/28/2024 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/18/2025 Approved TROY SANDERS
PLUMBING-Rough 7/10/2025 Not Ready for Inspection THOMAS FINNILA
Wood Frame 7/10/2025 Partial Approval THOMAS FINNILA
Special/Order Compliance 9/29/2025 Partial Inspection THOMAS FINNILA
Deputy Wood Construction 10/3/2025 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 10/10/2025 Partial Approval THOMAS FINNILA
Green Building Rough 10/10/2025 Partial Approval THOMAS FINNILA
Insulation 10/15/2025 Partial Approval ROBERT GOLD
Drywall Nailing 10/17/2025 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 10/17/2025 Corrections Issued THOMAS FINNILA
Wood Frame 12/24/2025 Partial Approval THOMAS FINNILA
Drywall Nailing 12/29/2025 Approved SEAN WIRCH
BUILDING-Rough-Frame 1/9/2026 Approved THOMAS FINNILA
Final 1/9/2026 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 1/9/2026 Approved THOMAS FINNILA
Final 1/27/2026 Corrections Issued THOMAS FINNILA
Green Building Final 1/27/2026 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/27/2026 SGSOV Approved THOMAS FINNILA
Smoke Detectors 1/27/2026 Approved THOMAS FINNILA