6321 W 84TH PL 90045

Certificate Information: 6321 W 84TH PL 90045

Application / Permit
24014-10000-03145
Plan Check / Job No.
B24LA13828
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
15'-7" X 20'-11" IRREGULAR SHAPED ADDITION TO THE SINGLE FAMILY DWELLING AND 4'-6" X 20'-11" PATIO COVER ADDITION - PER ENGINEER
Permit Issued
Issued on 9/13/2024
Issuing Office
Current Status
CofO Issued on 7/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2024 APPLICANT
Assigned to Plan Check Engineer 7/23/2024 DANIEL ABRAMYAN
Corrections Issued 7/24/2024 DANIEL ABRAMYAN
Plan Check Approved 9/12/2024 DANIEL ABRAMYAN
Issued 9/13/2024 APPLICANT
CofO in Progress 7/7/2025 DAVID FEILER
Permit Finaled 7/7/2025 RICHARD STEINBACH
CofO Issued 7/7/2025 RICHARD STEINBACH
Permit Finaled 7/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 8/8/2024 FREDDY GARCIA
Roof/Waste drainage to street Cleared 8/19/2024 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 8/27/2024 KIMBERLY HERNANDEZ

Contact Information

Contractor Sharp Builders Construction Inc; Lic. No.: 884884-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/19/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 10/10/2024 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval TEMISTOCLES CAAL
Insulation 10/16/2024 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 10/29/2024 Not Ready for Inspection MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Partial Approval MICHAEL ALLEN
Green Building Rough 10/29/2024 Not Ready for Inspection MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 11/27/2024 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 11/27/2024 Partial Approval MICHAEL ALLEN
Deputy Drilled-In Anchors 12/6/2024 Conditional Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 12/11/2024 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 1/6/2025 Approved MICHAEL ALLEN
HVAC-Rough 1/6/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 1/6/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 1/6/2025 Approved MICHAEL ALLEN
Insulation 1/10/2025 Approved MICHAEL ALLEN
Shower Pan 1/10/2025 Approved MICHAEL ALLEN
Drywall Nailing 1/14/2025 Approved MICHAEL ALLEN
Green Building Rough 1/14/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 1/14/2025 Not Ready for Inspection MICHAEL ALLEN
Interior/Exterior Lathing 1/16/2025 Approved JAYLIN GRAVITTE
Special/Order Compliance 1/16/2025 Partial Inspection BOBBY KEY
BUILDING-Rough-Frame 7/1/2025 Approved RUBEN RIVAS
ELECTRICAL-Final 7/1/2025 Approved RUBEN RIVAS
Final 7/1/2025 Corrections Issued RUBEN RIVAS
Footing/Foundation/Slab 7/1/2025 Approved RUBEN RIVAS
Green Building Final 7/1/2025 Approved RUBEN RIVAS
HVAC-Final 7/1/2025 Approved RUBEN RIVAS
PLUMBING-Final 7/1/2025 Approved RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Approved RUBEN RIVAS
Smoke Detectors 7/1/2025 Corrections Issued RUBEN RIVAS
Final 7/3/2025 OK to Issue CofO RUBEN RIVAS
Smoke Detectors 7/3/2025 Approved RUBEN RIVAS