5522 1/2 E STRATFORD ROAD 90042
Certificate Information: 5522 1/2 E STRATFORD ROAD 90042
- Application / Permit
- 24014-10000-03126
- Plan Check / Job No.
- B24LA13759
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERT (E) GARAGE TO ADU, WITH 2ND STORY ADDITION. DETACHED ADU PER LAMC 12.22 A.33 (c) and (d).
- Permit Issued
- Issued on 8/17/2025
- Issuing Office
- Current Status
- Issued on 8/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | ADRIANA LOPEZ |
| Corrections Issued | 11/2/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 11/15/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 4/15/2025 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 7/2/2025 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 7/17/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 8/13/2025 | ADRIANA LOPEZ |
| Issued | 8/17/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/21/2025 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 2/21/2025 | JUSTIN BICOL |
| Sewer availability | Cleared | 2/21/2025 | JUSTIN BICOL |
| Grading Pre-Inspection | Cleared | 2/21/2025 | JONATHAN HOM |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2025 | JUSTIN BICOL |
| GPI Written Notices | Cleared | 7/2/2025 | ADRIANA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 28531 PALOS VERDES DR EAST RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/14/2026 | Partial Inspection | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 2/6/2026 | Conditional Approval | DAVID WILLIAMS |
| Footing/Foundation/Slab | 2/12/2026 | Corrections Issued | DAVID WILLIAMS |
| PLUMBING-Rough | 2/12/2026 | Approved | DAVID WILLIAMS |
| Footing/Foundation/Slab | 2/25/2026 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2026 | Partial Approval | DAVID WILLIAMS |
| Green Building Rough | 3/6/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 4/14/2026 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 4/14/2026 | Corrections Issued | DAVID WILLIAMS |
| PLUMBING-Rough | 4/14/2026 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 4/21/2026 | Approved | DAVID WILLIAMS |
| Green Building Rough | 4/21/2026 | Approved | DAVID WILLIAMS |
| Insulation | 4/27/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 4/27/2026 | Partial Approval | DAVID WILLIAMS |
| Drywall Nailing | 4/30/2026 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2026 | Approved | DAVID WILLIAMS |
| Sewer | 7/14/2026 | Corrections Issued | NICHOLAS LOPEZ |