6942 N QUAKERTOWN AVE 91306

Certificate Information: 6942 N QUAKERTOWN AVE 91306

Application / Permit
24014-10000-03122
Plan Check / Job No.
B24LA13741
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major Remodel and Addition (860 SF) to (E) Single Family Dwelling to relocate and extend kitchen, new laundry, new bedroom, and new bathroom . Interior Remodel and reconfigure interior floor plan layout . Reframe and alter roof shape . ** NFPA 13D Fire Sprinklers Throughout **
Permit Issued
Issued on 12/6/2024
Issuing Office
Valley
Current Status
Issued on 12/6/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/17/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 GEORGE ALVAREZ
Corrections Issued 7/30/2024 GEORGE ALVAREZ
Building Plans Picked Up 8/1/2024 APPLICANT
Plan Check Approved 11/22/2024 NEHEMIAS RAMOS
Issued 12/6/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/9/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/9/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/12/2024 BIAINA HARITUNIAN
ZI Cleared 11/7/2024 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/21/2025 Not Ready for Inspection ALEXANDER HANDY
Underground Mechanical 2/21/2025 Approved ALEXANDER HANDY
Deputy Drilled-In Anchors 2/28/2025 Approved ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 2/28/2025 Approved ALEXANDER HANDY
Footing/Foundation/Slab 2/28/2025 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Partial Approval SCOTT SOBEL
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 6/6/2025 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 6/20/2025 Not Ready for Inspection SCOTT SOBEL
Green Building Rough 6/20/2025 Approved SCOTT SOBEL
Rough-Elec/Plmb/HVAC 6/20/2025 Corrections Issued SCOTT SOBEL
BUILDING-Rough-Frame 7/18/2025 Approved ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 7/18/2025 Approved ALEXANDER HANDY
Verify Sprinkler Sign Off 7/18/2025 Approved ALEXANDER HANDY
Insulation 7/22/2025 Approved ALEXANDER HANDY
Drywall Nailing 7/29/2025 Approved ARUTYUN MADATYAN
Service/Power Release 9/11/2025 Not Ready for Inspection JUAN ALVARADO
Shower Pan 9/11/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 9/23/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Final 11/20/2025 Not Ready for Inspection ALEXANDER HANDY
Service/Power Release 11/20/2025 Approved ALEXANDER HANDY
Final 6/18/2026 Corrections Issued ALEXANDER HANDY
Green Building Final 6/18/2026 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 6/18/2026 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 6/18/2026 Approved ALEXANDER HANDY