1648 W 213TH ST 90501
Certificate Information: 1648 W 213TH ST 90501
- Application / Permit
- 24014-10000-03118
- Plan Check / Job No.
- B24LA13727
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 6' X 6'6" ADDITION TO FRONT OF SFD AND 15'11" X 20'4-1/4" IRREG SHAPED ADDITION TO REAR OF SFD (237 SF) TO ADD NEW BEDROOM, BATHROOM, AND CLOSET AND EXTEND/REMODEL KITCHEN. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 9/10/2024
- Issuing Office
- Current Status
- CofO Issued on 1/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2024 | MADISON ODELL |
| Corrections Issued | 7/23/2024 | MADISON ODELL |
| Applicant returned to address corrections | 8/16/2024 | MADISON ODELL |
| Applicant returned to address corrections | 8/31/2024 | MADISON ODELL |
| Applicant returned to address corrections | 9/7/2024 | MADISON ODELL |
| Plan Check Approved | 9/9/2024 | MADISON O'DELL |
| Issued | 9/10/2024 | APPLICANT |
| CofO in Progress | 1/29/2025 | EUGENE CASSIDY |
| CofO Issued | 1/29/2025 | ANSON MAGLASANG |
| Permit Finaled | 1/29/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/15/2024 | JILVER MAZARIEGOS |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 8/29/2024 | JILVER MAZARIEGOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xi,, Wang; Lic. No.: C85148 | 422 FALLINGSTAR IRVINE, CA 92614 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/26/2024 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/26/2024 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 9/26/2024 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 9/26/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2024 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 10/3/2024 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 10/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/16/2024 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/16/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 10/16/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/16/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/21/2024 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 10/21/2024 | Approved | EUGENE CASSIDY |
| Insulation | 10/25/2024 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/25/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 10/28/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/29/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Drywall Nailing | 11/4/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/4/2024 | Partial Approval | EUGENE CASSIDY |
| Shower Pan | 11/26/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/5/2024 | Approved | EUGENE CASSIDY |
| Final | 12/20/2024 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 12/20/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 1/24/2025 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 1/24/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/28/2025 | Approved | EUGENE CASSIDY |
| Final | 1/28/2025 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 1/28/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/28/2025 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 1/28/2025 | Approved | EUGENE CASSIDY |