1648 W 213TH ST 90501

Certificate Information: 1648 W 213TH ST 90501

Application / Permit
24014-10000-03118
Plan Check / Job No.
B24LA13727
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 6' X 6'6" ADDITION TO FRONT OF SFD AND 15'11" X 20'4-1/4" IRREG SHAPED ADDITION TO REAR OF SFD (237 SF) TO ADD NEW BEDROOM, BATHROOM, AND CLOSET AND EXTEND/REMODEL KITCHEN. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 9/10/2024
Issuing Office
Current Status
CofO Issued on 1/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2024 APPLICANT
Assigned to Plan Check Engineer 7/22/2024 MADISON ODELL
Corrections Issued 7/23/2024 MADISON ODELL
Applicant returned to address corrections 8/16/2024 MADISON ODELL
Applicant returned to address corrections 8/31/2024 MADISON ODELL
Applicant returned to address corrections 9/7/2024 MADISON ODELL
Plan Check Approved 9/9/2024 MADISON O'DELL
Issued 9/10/2024 APPLICANT
CofO in Progress 1/29/2025 EUGENE CASSIDY
CofO Issued 1/29/2025 ANSON MAGLASANG
Permit Finaled 1/29/2025 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/15/2024 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 8/29/2024 JILVER MAZARIEGOS
Sewer availability Cleared 8/29/2024 JILVER MAZARIEGOS

Contact Information

Contractor Owner-Builder       ,
Engineer Xi,, Wang; Lic. No.: C85148 422 FALLINGSTAR      IRVINE, CA 92614

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/26/2024 Approved EUGENE CASSIDY
Footing/Foundation/Slab 9/26/2024 Approved EUGENE CASSIDY
METHANE-Barrier 9/26/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 9/26/2024 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 10/3/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 10/11/2024 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 10/11/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 10/16/2024 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 10/16/2024 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 10/16/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 10/16/2024 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 10/21/2024 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 10/21/2024 Approved EUGENE CASSIDY
Insulation 10/25/2024 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 10/25/2024 Not Ready for Inspection EUGENE CASSIDY
Insulation 10/28/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/29/2024 Not Ready for Inspection EUGENE CASSIDY
Drywall Nailing 11/4/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/4/2024 Partial Approval EUGENE CASSIDY
Shower Pan 11/26/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/5/2024 Approved EUGENE CASSIDY
Final 12/20/2024 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 12/20/2024 Not Ready for Inspection EUGENE CASSIDY
Final 1/24/2025 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 1/24/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 1/28/2025 Approved EUGENE CASSIDY
Final 1/28/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 1/28/2025 Approved EUGENE CASSIDY
PLUMBING-Final 1/28/2025 Approved EUGENE CASSIDY
Smoke Detectors 1/28/2025 Approved EUGENE CASSIDY