543 N ORANGE DR 90036
Certificate Information: 543 N ORANGE DR 90036
- Application / Permit
- 24014-10000-03084
- Plan Check / Job No.
- B24LA13534
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT FROM (E) ATTIC TO CLOSET. INSTALL TO (N) SPIRAL STAIRWAY
- Permit Issued
- Issued on 8/23/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | KHUONG TRUONG |
| Corrections Issued | 7/23/2024 | KHUONG TRUONG |
| Quality Review Completed | 7/23/2024 | KEN GILL |
| Building Plans Picked Up | 7/26/2024 | APPLICANT |
| Plan Check Approved | 8/20/2024 | KHUONG TRUONG |
| Issued | 8/23/2024 | APPLICANT |
| CofO in Progress | 9/30/2025 | CRAIG VAUGHAN |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
| CofO Issued | 10/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | 777 Painting & Construction Inc; Lic. No.: 503332-B | 1027 4TH AVENUE LOS ANGELES, CA 90019 |
| Engineer | Kim,, Seung; Lic. No.: S5909 | 9934 CEDAR CT CYPRESS, CA 90630 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/25/2025 | Corrections Issued | CRAIG VAUGHAN |
| METHANE-Barrier | 7/25/2025 | Approved | CRAIG VAUGHAN |
| METHANE-Subgrade | 7/25/2025 | Approved | CRAIG VAUGHAN |
| Wood Frame | 7/25/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/6/2025 | Approved | CRAIG VAUGHAN |
| Wood Frame | 8/6/2025 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 8/11/2025 | Partial Approval | ROY SPAULDING |
| Drywall Nailing | 8/12/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | CRAIG VAUGHAN |
| Final | 9/24/2025 | OK to Issue CofO | CRAIG VAUGHAN |
| Green Building Final | 9/24/2025 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 9/24/2025 | Approved | CRAIG VAUGHAN |
| METHANE-Final | 9/24/2025 | Approved | CRAIG VAUGHAN |
| METHANE-Rough | 9/24/2025 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 9/24/2025 | Approved | CRAIG VAUGHAN |