868 E COMMONWEALTH AVE 90291
Certificate Information: 868 E COMMONWEALTH AVE 90291
- Application / Permit
- 24014-10000-03040
- Plan Check / Job No.
- B24LA13322
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan CONVERSION OF (E) GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 12/12/2024
- Issuing Office
- Current Status
- CofO Issued on 7/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/8/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 8/14/2024 | TU HUA |
| Applicant returned to address corrections | 9/19/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 10/1/2024 | MAHNAZ NOURHASHEMI |
| Issued | 12/12/2024 | APPLICANT |
| CofO in Progress | 7/8/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 7/17/2025 | RICHARD STEINBACH |
| CofO Issued | 7/17/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/17/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 8/19/2024 | NOAH MCCOY |
| Address approval | Cleared | 8/26/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 8/26/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 9/13/2024 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Sound Structures Inc; Lic. No.: 923028-B | , |
| Engineer | Bartelle,, Kristofer Grimm; Lic. No.: C84617 | 22910 BURBANK BLVD WOODLAND HILLS, CA 91367 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/27/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 1/30/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 1/31/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 2/20/2025 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/26/2025 | Approved | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 4/21/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/21/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 4/21/2025 | Approved | JESUS RODRIGUEZ |
| Rough-Elec/Plmb/HVAC | 4/21/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 4/30/2025 | Approved | JAYLIN GRAVITTE |
| Special/Order Compliance | 4/30/2025 | Partial Inspection | BOBBY KEY |
| Drywall Nailing | 5/5/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 6/23/2025 | Approved | JESUS RODRIGUEZ |
| Gas Test | 6/26/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/26/2025 | Approved | JESUS RODRIGUEZ |
| Final | 7/3/2025 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 7/3/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 7/3/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/3/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 7/3/2025 | Approved | JESUS RODRIGUEZ |