868 E COMMONWEALTH AVE 90291

Certificate Information: 868 E COMMONWEALTH AVE 90291

Application / Permit
24014-10000-03040
Plan Check / Job No.
B24LA13322
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan CONVERSION OF (E) GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 12/12/2024
Issuing Office
Current Status
CofO Issued on 7/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 MAHNAZ NOURHASHEMI
Corrections Issued 8/8/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 8/14/2024 TU HUA
Applicant returned to address corrections 9/19/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 10/1/2024 MAHNAZ NOURHASHEMI
Issued 12/12/2024 APPLICANT
CofO in Progress 7/8/2025 JESUS RODRIGUEZ
Permit Finaled 7/17/2025 RICHARD STEINBACH
CofO Issued 7/17/2025 RICHARD STEINBACH
Permit Finaled 7/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 8/19/2024 NOAH MCCOY
Address approval Cleared 8/26/2024 LIAM ODONOVAN
Sewer availability Cleared 8/26/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 9/4/2024 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 9/13/2024 VLADIMIR ARUTYUNYAN

Contact Information

Contractor Sound Structures Inc; Lic. No.: 923028-B       ,
Engineer Bartelle,, Kristofer Grimm; Lic. No.: C84617 22910 BURBANK BLVD      WOODLAND HILLS, CA 91367

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/27/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 1/30/2025 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 1/31/2025 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 2/20/2025 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 3/26/2025 Approved JAYLIN GRAVITTE
BUILDING-Rough-Frame 4/21/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 4/21/2025 Approved JESUS RODRIGUEZ
Green Building Rough 4/21/2025 Approved JESUS RODRIGUEZ
Rough-Elec/Plmb/HVAC 4/21/2025 Approved JESUS RODRIGUEZ
Insulation 4/30/2025 Approved JAYLIN GRAVITTE
Special/Order Compliance 4/30/2025 Partial Inspection BOBBY KEY
Drywall Nailing 5/5/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 6/23/2025 Approved JESUS RODRIGUEZ
Gas Test 6/26/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 6/26/2025 Approved JESUS RODRIGUEZ
Final 7/3/2025 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 7/3/2025 Approved JESUS RODRIGUEZ
HVAC-Final 7/3/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/3/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 7/3/2025 Approved JESUS RODRIGUEZ