4936 S COOLIDGE AVE 90230

Certificate Information: 4936 S COOLIDGE AVE 90230

Application / Permit
24014-10000-03038
Plan Check / Job No.
B24LA13299
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Addition and remodel of existing single family residence. ***13D SPRINKLER REQUIRED***
Permit Issued
Issued on 11/25/2024
Issuing Office
Current Status
CofO Issued on 7/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 KHUONG TRUONG
Corrections Issued 7/20/2024 KHUONG TRUONG
Quality Review Completed 7/24/2024 GARO TELMI
Applicant returned to address corrections 8/19/2024 KHUONG TRUONG
Plan Check Approved 9/27/2024 KHUONG TRUONG
Issued 11/25/2024 APPLICANT
CofO in Progress 7/8/2025 DAVID FEILER
Permit Finaled 7/10/2025 RICHARD STEINBACH
CofO Issued 7/10/2025 RICHARD STEINBACH
Permit Finaled 7/10/2025 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 8/2/2024 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 8/7/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 8/7/2024 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 8/19/2024 KIMBERLY HERNANDEZ
Trees in Parkway Cleared 9/20/2024 ADALBERTO VERA
Permit Cleared 9/25/2024 KIMBERLY HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Dass,, Praveen Kumar; Lic. No.: C74200 2801 ALTON PARKWAY   #205    IRVINE, CA 92606

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/27/2024 Partial Approval MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 12/6/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 12/6/2024 Not Ready for Inspection JESUS PINEDA
Excavation/Setback/Form/Re-Bar 12/9/2024 Corrections Issued JESUS PINEDA
Excavation/Setback/Form/Re-Bar 12/11/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 12/11/2024 Not Ready for Inspection JESUS PINEDA
Excavation/Setback/Form/Re-Bar 12/16/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 12/16/2024 Not Ready for Inspection JESUS PINEDA
Footing/Foundation/Slab 12/18/2024 Approved JESUS PINEDA
Sewer 12/27/2024 Not Ready for Inspection JESUS PINEDA
Special/Order Compliance 12/27/2024 Corrections Issued JESUS PINEDA
Sewer 12/31/2024 Approved JESUS PINEDA
Underground Mechanical 12/31/2024 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 3/7/2025 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Approved HERBERT GIRON
HVAC-Rough 3/7/2025 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 3/7/2025 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 3/21/2025 Partial Approval RUBEN RIVAS
Green Building Rough 3/21/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 3/21/2025 Corrections Issued RUBEN RIVAS
MERV13>=Rough 3/21/2025 Approved RUBEN RIVAS
PLUMBING-Rough 3/21/2025 Approved RUBEN RIVAS
Special/Order Compliance 3/21/2025 Partial Inspection STEPHANIE SWANSON
HVAC-Rough 3/27/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/27/2025 Approved JESUS RODRIGUEZ
Special/Order Compliance 3/27/2025 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 4/1/2025 Approved JESUS RODRIGUEZ
Green Building Rough 4/1/2025 Approved JESUS RODRIGUEZ
Insulation 4/1/2025 Conditional Approval JESUS RODRIGUEZ
Verify Sprinkler Sign Off 4/1/2025 Approved JESUS RODRIGUEZ
Insulation 4/10/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 4/16/2025 Approved JAYLIN GRAVITTE
Shower Pan 4/23/2025 Not Ready for Inspection JAYLIN GRAVITTE
Shower Pan 4/28/2025 Approved TEMISTOCLES CAAL
Special/Order Compliance 4/28/2025 Partial Inspection HERBERT GIRON
Special/Order Compliance 4/28/2025 Partial Inspection TEMISTOCLES CAAL
Interior/Exterior Lathing 5/5/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 6/24/2025 Approved MICHAEL ALLEN
Final 6/24/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 6/24/2025 Approved MICHAEL ALLEN
HVAC-Final 6/24/2025 Conditional Approval MICHAEL ALLEN
MERV13>=Final 6/24/2025 Approved MICHAEL ALLEN
PLUMBING-Final 6/24/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV No Gas MICHAEL ALLEN
Smoke Detectors 6/24/2025 Approved MICHAEL ALLEN
Final 6/26/2025 Corrections Issued MICHAEL ALLEN
HVAC-Final 6/26/2025 Approved MICHAEL ALLEN
Final 7/8/2025 OK to Issue CofO DAVID FEILER