3910-3912 S MCLAUGHLIN AVE 90066
Certificate Information: 3910-3912 S MCLAUGHLIN AVE 90066
- Application / Permit
- 24014-10000-03029
- Plan Check / Job No.
- B24LA13256
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (ePLAN) Addition of 1-story accessory dwelling unit, 2-car garage, and 2nd floor addition to existing 1-story single family dwelling to create 2-story single family dwelling with attached 1-story accessory dwelling unit and garage per engineer details.
- Permit Issued
- Issued on 11/23/2024
- Issuing Office
- Current Status
- CofO Issued on 11/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | VICTOR CHEN |
| Corrections Issued | 7/13/2024 | VICTOR CHEN |
| Quality Review Completed | 8/6/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 10/10/2024 | VICTOR CHEN |
| Applicant returned to address corrections | 11/3/2024 | VICTOR CHEN |
| Applicant returned to address corrections | 11/12/2024 | VICTOR CHEN |
| Applicant returned to address corrections | 11/19/2024 | VICTOR CHEN |
| Applicant returned to address corrections | 11/21/2024 | VICTOR CHEN |
| Plan Check Approved | 11/22/2024 | VICTOR CHEN |
| Issued | 11/23/2024 | APPLICANT |
| CofO in Progress | 11/14/2025 | WILBER ROSALES |
| Permit Finaled | 11/20/2025 | RICHARD STEINBACH |
| CofO Issued | 11/20/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/20/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/7/2024 | DARIN LAM |
| Permit | Cleared | 8/7/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2024 | DARIN LAM |
| Sewer availability | Cleared | 8/8/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 8/20/2024 | DARIN LAM |
| Specific Plan | Cleared | 8/20/2024 | FREDDY GARCIA |
| Disturb/Remove Protected Trees | Cleared | 8/23/2024 | RICHARD SANCHEZ |
| Trees in Parkway | Cleared | 8/28/2024 | ADALBERTO VERA |
| Construction near power lines | Cleared | 9/23/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bakhshi,, Brian; Lic. No.: L9767 | 8758 CASHIO ST. APT 10 W LOS ANGELES, CA 90035 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/31/2024 | Partial Approval | JESUS PINEDA |
| Sewer | 12/31/2024 | Approved | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 1/7/2025 | Corrections Issued | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 1/10/2025 | Corrections Issued | JESUS PINEDA |
| Deputy Reinf. Concrete | 1/13/2025 | Conditional Approval | BOBBY KEY |
| Deputy Steel/Welding | 1/30/2025 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Wood Construction | 2/24/2025 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 2/24/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 3/4/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 3/5/2025 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 3/6/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 3/10/2025 | No Access for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Rough | 3/11/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Rough | 3/17/2025 | Not Ready for Inspection | RUBEN RIVAS |
| PLUMBING-Rough | 3/17/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 3/17/2025 | Partial Inspection | BOBBY KEY |
| Special/Order Compliance | 3/21/2025 | Partial Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 4/8/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Interior/Exterior Lathing | 4/16/2025 | Partial Approval | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 4/21/2025 | Partial Approval | MICHAEL ALLEN |
| Green Building Rough | 4/21/2025 | Approved | MICHAEL ALLEN |
| Insulation | 4/21/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 4/25/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 4/28/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 4/30/2025 | Approved | JAYLIN GRAVITTE |
| Special/Order Compliance | 4/30/2025 | Partial Inspection | BOBBY KEY |
| Gas Test | 7/28/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 8/22/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 8/22/2025 | Approved | WILBER ROSALES |
| Service/Power Release | 8/22/2025 | Not Ready for Inspection | WILBER ROSALES |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | WILBER ROSALES |
| Final | 8/29/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 8/29/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 8/29/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Not Ready | WILBER ROSALES |
| Smoke Detectors | 8/29/2025 | Approved | WILBER ROSALES |
| Final | 11/3/2025 | Conditional Approval | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV Approved | WILBER ROSALES |
| Final | 11/13/2025 | OK to Issue CofO | WILBER ROSALES |
| Service/Power Release | 11/13/2025 | Approved | WILBER ROSALES |