761 N ALMAR AVE 90272
Certificate Information: 761 N ALMAR AVE 90272
- Application / Permit
- 24014-10000-03023
- Plan Check / Job No.
- B24LA13220
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR ADDITION AND REMODELING TO (E) ONE STORY SFD WITH ATTACHED TWO CAR GARAGE TO BECOME A TWO STORY SFD W/ ATTACHED TWO CAR GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 12/19/2024
- Issuing Office
- Current Status
- Issued on 12/19/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | SERGIO GUTIERREZ |
| Corrections Issued | 7/16/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 7/23/2024 | JOHNNY WU |
| Plan Check Approved | 12/18/2024 | SERGIO GUTIERREZ |
| Issued | 12/19/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 8/6/2024 | LIAM ODONOVAN |
| Hydrant and Access approval | Cleared | 10/18/2024 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 11/4/2024 | ERNEST TSE |
| Permit | Cleared | 11/19/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 11/19/2024 | VLADIMIR ARUTYUNYAN |
| GPI Written Notices | Cleared | 12/18/2024 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 12/18/2024 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Montemayor,, G F; Lic. No.: C25258 | 1617 S WAVERLY GLEN WAY HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/2/2025 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 9/23/2025 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 10/29/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 10/29/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Deputy Wood Construction | 12/9/2025 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 12/10/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 12/10/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2026 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 1/21/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 1/21/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 2/18/2026 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 2/23/2026 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 2/24/2026 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 2/25/2026 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 3/18/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 4/14/2026 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 4/15/2026 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 4/15/2026 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 4/15/2026 | Approved | MEL KHACHATOURIAN |
| Insulation | 4/22/2026 | Approved | BOBBY KEY |
| Shower Pan | 4/23/2026 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/4/2026 | Approved | BOBBY KEY |
| Drywall Nailing | 5/8/2026 | Approved | MEL KHACHATOURIAN |