838 E PALMS BLVD 90291

Certificate Information: 838 E PALMS BLVD 90291

Application / Permit
24014-10000-03020
Plan Check / Job No.
B24LA13187
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
EXTERIOR/INTERIOR REMODEL AND ADDITION TO (E) DETACHED GARAGE. ADDITION FOR NEW HALF BATH COASTAL
Permit Issued
Issued on 12/17/2025
Issuing Office
West Los Angeles
Current Status
Issued on 12/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/10/2024 APPLICANT
Assigned to Plan Check Engineer 7/10/2024 NEHEMIAS RAMOS
Corrections Issued 7/10/2024 NEHEMIAS RAMOS
Plan Check Approved 11/1/2024 KELVIN CHUONG
Issued 12/17/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/12/2024 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 7/12/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 7/12/2024 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 7/17/2024 BRENDEN HAWK
Miscellaneous Cleared 7/22/2024 ROSALINDA MEZA
Miscellaneous Cleared 7/22/2024 ROSALINDA MEZA
Miscellaneous Cleared 7/22/2024 ROSALINDA MEZA
Specific Plan Cleared 8/21/2024 PEDRO AYALA
Specific Plan Cleared 8/22/2024 LUIS LOPEZ
Coastal Zone Cleared 9/19/2024 CLAUDE GOODING

Contact Information

Contractor X Tech Construction; Lic. No.: 1125377-B 3440 WESLEY ST      CULVER CITY, CA 90232

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

PLUMBING-Final 6/8/2026   

Inspection Request History

Pre-Inspection 12/22/2025 Corrections Issued RUBEN RIVAS
Wood Frame 1/14/2026 Partial Approval RUBEN RIVAS
Underground Mechanical 1/22/2026 Approved RUBEN RIVAS
Wood Frame 1/22/2026 Not Ready for Inspection RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 1/27/2026 Approved RUBEN RIVAS
Footing/Foundation/Slab 1/27/2026 Approved RUBEN RIVAS
BUILDING-Rough-Frame 2/20/2026 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 2/20/2026 Corrections Issued RUBEN RIVAS
HVAC-Rough 2/20/2026 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 2/24/2026 Not Ready for Inspection RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 2/24/2026 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 2/24/2026 Not Ready for Inspection RUBEN RIVAS
Rough-Elec/Plmb/HVAC 2/24/2026 Not Ready for Inspection RUBEN RIVAS
Wood Frame 2/24/2026 Not Ready for Inspection RUBEN RIVAS
BUILDING-Rough-Frame 3/3/2026 Approved RUBEN RIVAS
Deputy Wood Construction 3/3/2026 Approved RUBEN RIVAS
ELECTRICAL-Rough 3/3/2026 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 3/3/2026 Approved RUBEN RIVAS
HVAC-Rough 3/3/2026 Approved RUBEN RIVAS
Interior/Exterior Lathing 4/16/2026 Approved RUBEN RIVAS
Insulation 4/22/2026 Approved RUBEN RIVAS
Drywall Nailing 4/29/2026 Approved RUBEN RIVAS