1908 N JONES AVE 90032

Certificate Information: 1908 N JONES AVE 90032

Application / Permit
24014-10000-03013
Plan Check / Job No.
B24LA13154
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to rear of (E) single family dwelling
Permit Issued
Issued on 10/10/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2024 APPLICANT
Assigned to Plan Check Engineer 7/15/2024 LAWRENCE QUIRANTE
Corrections Issued 7/15/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 7/22/2024 APPLICANT
Applicant returned to address corrections 8/21/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 9/4/2024 DANIEL SANJUAN
Applicant returned to address corrections 9/20/2024 SUNMIN LEE
Plan Check Approved 10/9/2024 ALEXANDER JOO
Issued 10/10/2024 APPLICANT
CofO in Progress 5/22/2025 LILIANA PORTILLO
Permit Finaled 5/23/2025 DEROLD HAUFF
CofO Issued 5/23/2025 DEROLD HAUFF
Permit Finaled 5/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/20/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 9/20/2024 CHRISTINA BRACO
Grading Pre-Inspection Cleared 10/9/2024 MICHAEL TEMPLE

Contact Information

Contractor Rios Juan Construction; Lic. No.: 876856-B 1311 N LUELLA DRIVE      LOS ANGELES, CA 90063
Engineer Li,, Pin-Ching; Lic. No.: C38408 18803 ALDRIDGE PLACE      ROWLAND HEIGHTS, CA 91748

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/31/2024 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 11/12/2024 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 11/14/2024 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 11/14/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Partial Approval LILIANA PORTILLO
Insulation 11/19/2024 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 11/19/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Approved JOHN QUINTANILLA
Green Building Rough 11/26/2024 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 12/11/2024 Approved WILLIAM SIERRA
ELECTRICAL-Rough 12/11/2024 Approved WILLIAM SIERRA
Green Building Rough 12/11/2024 Approved WILLIAM SIERRA
HVAC-Rough 12/11/2024 Approved WILLIAM SIERRA
PLUMBING-Rough 12/11/2024 Approved WILLIAM SIERRA
Shower Pan 12/11/2024 Approved WILLIAM SIERRA
Insulation 12/18/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/18/2024 Approved LILIANA PORTILLO
Drywall Nailing 12/23/2024 Approved ANTHONY RAMOS
Final 5/13/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/13/2025 Approved LILIANA PORTILLO
Green Building Final 5/13/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/13/2025 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 5/13/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 5/21/2025 Approved LILIANA PORTILLO
Final 5/21/2025 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 5/21/2025 Approved LILIANA PORTILLO
PLUMBING-Final 5/21/2025 Approved LILIANA PORTILLO
Smoke Detectors 5/21/2025 Approved LILIANA PORTILLO