7900 S DENROCK AVE 90045
Certificate Information: 7900 S DENROCK AVE 90045
- Application / Permit
- 24014-10000-03012
- Plan Check / Job No.
- B24LA13153
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: REMODEL, (N) 11'-6" X 30'-0" ADDITION TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/20/2025
- Issuing Office
- Current Status
- Issued on 5/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2024 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 7/13/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 7/31/2024 | GIOVANNY CHAVEZ |
| Issued | 5/20/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/17/2024 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 7/17/2024 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 7/18/2024 | RICHARD WOO |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | ANDREA SAINT-ANTONIN |
| Grading Pre-Inspection | Cleared | 7/29/2024 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Guirguis,, Diaa; Lic. No.: NA40731 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/20/2026 | Corrections Issued | MICHAEL ALLEN |
| Footing/Foundation/Slab | 2/25/2026 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/9/2026 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 3/9/2026 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2026 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/16/2026 | Approved | JESUS PINEDA |
| HVAC-Rough | 4/16/2026 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 4/16/2026 | Approved | JESUS PINEDA |