891 1/2 S NORTON AVE 90005
Certificate Information: 891 1/2 S NORTON AVE 90005
- Application / Permit
- 24014-10000-03011
- Plan Check / Job No.
- B24LA13149
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story ADU per LAMC 12.22 A.33 (c)-(d). "COMPLY WITH DEPARTMENT ORDER effective date 06/18/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 12/13/2024
- Issuing Office
- Current Status
- CofO Issued on 1/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2024 | ADAM HEGAZI |
| Corrections Issued | 7/17/2024 | ADAM HEGAZI |
| Building Plans Picked Up | 8/5/2024 | APPLICANT |
| Plan Check Approved | 12/13/2024 | AMY GUEVARRA |
| Issued | 12/13/2024 | APPLICANT |
| CofO in Progress | 9/30/2025 | RUBEN PEREZ |
| Permit Finaled | 1/8/2026 | DANIEL SANCHEZ |
| CofO Issued | 1/8/2026 | DANIEL SANCHEZ |
| Permit Finaled | 1/8/2026 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 11/21/2024 | CELINA MORENO |
| Sewer availability | Cleared | 11/21/2024 | CELINA MORENO |
| HPOZ | Cleared | 11/26/2024 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 11/26/2024 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 11/26/2024 | MICAELA TORRES-GIL |
| Construction near power lines | Cleared | 12/12/2024 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/19/2024 | Approved | RUBEN PEREZ |
| Footing/Foundation/Slab | 1/7/2025 | Not Ready for Inspection | PETER RUBIO |
| Footing/Foundation/Slab | 1/21/2025 | Not Ready for Inspection | RUBEN PEREZ |
| Footing/Foundation/Slab | 1/23/2025 | Approved | RUBEN PEREZ |
| ELECTRICAL-Rough | 4/14/2025 | Partial Approval | RUBEN PEREZ |
| PLUMBING-Rough | 4/14/2025 | Partial Approval | RUBEN PEREZ |
| Wood Frame | 4/14/2025 | Not Ready for Inspection | RUBEN PEREZ |
| ELECTRICAL-Rough | 4/30/2025 | Partial Approval | PETER RUBIO |
| HVAC-Rough | 4/30/2025 | Approved | PETER RUBIO |
| PLUMBING-Rough | 4/30/2025 | Not Ready for Inspection | PETER RUBIO |
| ELECTRICAL-Rough | 5/7/2025 | Not Ready for Inspection | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Approved | PETER RUBIO |
| Interior/Exterior Lathing | 5/7/2025 | Not Ready for Inspection | PETER RUBIO |
| PLUMBING-Rough | 5/7/2025 | Approved | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2025 | Approved | PETER RUBIO |
| Shower Pan | 5/8/2025 | Approved | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Approved | RUBEN PEREZ |
| Insulation | 5/12/2025 | Approved | RUBEN PEREZ |
| Drywall Nailing | 5/14/2025 | Approved | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Approved | PETER RUBIO |
| Interior/Exterior Lathing | 6/2/2025 | Approved | PETER RUBIO |
| BUILDING-Rough-Frame | 9/18/2025 | Approved | PETER RUBIO |
| Final | 9/18/2025 | Not Ready for Inspection | PETER RUBIO |
| Green Building Final | 9/18/2025 | Approved | PETER RUBIO |
| Green Building Rough | 9/18/2025 | Approved | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Approved | PETER RUBIO |
| Service/Power Release | 9/18/2025 | Approved | PETER RUBIO |
| Smoke Detectors | 9/18/2025 | Approved | PETER RUBIO |
| Verify Sprinkler Sign Off | 9/18/2025 | Approved | PETER RUBIO |
| Final | 9/29/2025 | OK to Issue CofO | RUBEN PEREZ |