17106 W GAULT ST 91406

Certificate Information: 17106 W GAULT ST 91406

Application / Permit
24014-10000-02979
Plan Check / Job No.
B24LA13066
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION AND INT. STR REMODEL TO (E) 1-STORY SFD -BLDG SPRINKLERD THRU-OUT
Permit Issued
Issued on 8/15/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 MAHNAZ NOURHASHEMI
Corrections Issued 7/15/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 7/19/2024 KEN GILL
Building Plans Picked Up 7/19/2024 APPLICANT
Plan Check Approved 8/6/2024 MAHNAZ NOURHASHEMI
Issued 8/15/2024 APPLICANT
CofO in Progress 2/5/2026 JON MCHUGH
Permit Finaled 4/25/2026 MICHAEL PELHAM
CofO Issued 4/25/2026 MICHAEL PELHAM
Permit Finaled 4/25/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 7/30/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 7/30/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 8/1/2024 EDGAR ALCARAZ
Sewer availability Cleared 8/1/2024 EDGAR ALCARAZ

Contact Information

Contractor Sarraf Contracting Inc; Lic. No.: 1074518-B 1024 DOLORITA AVE      GLENDALE, CA 91208

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/26/2024 Partial Approval JON MCHUGH
Footing/Foundation/Slab 8/26/2024 Partial Approval JON MCHUGH
Deputy Drilled-In Anchors 8/27/2024 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Corrections Issued JON MCHUGH
PLUMBING-Rough 9/13/2024 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Partial Approval JON MCHUGH
PLUMBING-Rough 9/17/2024 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Partial Approval JON MCHUGH
Insulation 9/23/2024 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 11/13/2024 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Partial Approval JON MCHUGH
PLUMBING-Rough 12/24/2024 Corrections Issued SCOTT SOBEL
ELECTRICAL-Rough 1/10/2025 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Corrections Issued JON MCHUGH
HVAC-Rough 1/10/2025 Corrections Issued JON MCHUGH
PLUMBING-Rough 1/10/2025 Not Ready for Inspection JON MCHUGH
Deputy Wood Construction 1/14/2025 Conditional Approval MORRIS JACKSON
BUILDING-Rough-Frame 1/17/2025 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 1/17/2025 Approved JON MCHUGH
Rough-Elec/Plmb/HVAC 1/17/2025 Corrections Issued JON MCHUGH
HVAC-Rough 1/29/2025 Approved JON MCHUGH
Shower Pan 1/29/2025 Approved JON MCHUGH
Verify Sprinkler Sign Off 1/29/2025 Approved JON MCHUGH
Interior/Exterior Lathing 2/19/2025 Corrections Issued JON MCHUGH
Interior/Exterior Lathing 2/24/2025 Partial Approval JON MCHUGH
BUILDING-Rough-Frame 2/27/2025 Approved JON MCHUGH
Green Building Rough 2/27/2025 Approved JON MCHUGH
Interior/Exterior Lathing 2/27/2025 Approved JON MCHUGH
ELECTRICAL-Rough 3/6/2025 Approved JON MCHUGH
Insulation 3/6/2025 Approved JON MCHUGH
PLUMBING-Rough 3/6/2025 Approved JON MCHUGH
Drywall Nailing 3/14/2025 Partial Approval JON MCHUGH
Final 10/15/2025 Not Ready for Inspection JON MCHUGH
Footing/Foundation/Slab 10/15/2025 Approved JON MCHUGH
Green Building Final 10/15/2025 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Not Ready JON MCHUGH
Smoke Detectors 10/15/2025 Not Ready for Inspection JON MCHUGH
Final 12/16/2025 Corrections Issued JON MCHUGH
Green Building Final 12/16/2025 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 12/16/2025 SGSOV Not Ready JON MCHUGH
Service/Power Release 12/16/2025 Approved JON MCHUGH
Smoke Detectors 12/16/2025 Not Ready for Inspection JON MCHUGH
Final 12/30/2025 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Not Ready JON MCHUGH
Smoke Detectors 12/30/2025 Approved JON MCHUGH
Final 1/21/2026 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 1/21/2026 SGSOV Not Ready JON MCHUGH
ELECTRICAL-Final 2/5/2026 Approved JON MCHUGH
Final 2/5/2026 OK to Issue CofO JON MCHUGH
HVAC-Final 2/5/2026 Approved JON MCHUGH
PLUMBING-Final 2/5/2026 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 2/5/2026 SGSOV Approved JON MCHUGH