17106 W GAULT ST 91406
Certificate Information: 17106 W GAULT ST 91406
- Application / Permit
- 24014-10000-02979
- Plan Check / Job No.
- B24LA13066
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION AND INT. STR REMODEL TO (E) 1-STORY SFD -BLDG SPRINKLERD THRU-OUT
- Permit Issued
- Issued on 8/15/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/15/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/19/2024 | KEN GILL |
| Building Plans Picked Up | 7/19/2024 | APPLICANT |
| Plan Check Approved | 8/6/2024 | MAHNAZ NOURHASHEMI |
| Issued | 8/15/2024 | APPLICANT |
| CofO in Progress | 2/5/2026 | JON MCHUGH |
| Permit Finaled | 4/25/2026 | MICHAEL PELHAM |
| CofO Issued | 4/25/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/25/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 8/1/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 8/1/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Sarraf Contracting Inc; Lic. No.: 1074518-B | 1024 DOLORITA AVE GLENDALE, CA 91208 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/26/2024 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 8/26/2024 | Partial Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 8/27/2024 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 9/13/2024 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 9/17/2024 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Partial Approval | JON MCHUGH |
| Insulation | 9/23/2024 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 11/13/2024 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 12/24/2024 | Corrections Issued | SCOTT SOBEL |
| ELECTRICAL-Rough | 1/10/2025 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2025 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 1/10/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 1/10/2025 | Not Ready for Inspection | JON MCHUGH |
| Deputy Wood Construction | 1/14/2025 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/17/2025 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Approved | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 1/17/2025 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 1/29/2025 | Approved | JON MCHUGH |
| Shower Pan | 1/29/2025 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 1/29/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 2/19/2025 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 2/24/2025 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 2/27/2025 | Approved | JON MCHUGH |
| Green Building Rough | 2/27/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 2/27/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 3/6/2025 | Approved | JON MCHUGH |
| Insulation | 3/6/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 3/6/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 3/14/2025 | Partial Approval | JON MCHUGH |
| Final | 10/15/2025 | Not Ready for Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 10/15/2025 | Approved | JON MCHUGH |
| Green Building Final | 10/15/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/15/2025 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 10/15/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 12/16/2025 | Corrections Issued | JON MCHUGH |
| Green Building Final | 12/16/2025 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 12/16/2025 | Approved | JON MCHUGH |
| Smoke Detectors | 12/16/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 12/30/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 12/30/2025 | Approved | JON MCHUGH |
| Final | 1/21/2026 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Not Ready | JON MCHUGH |
| ELECTRICAL-Final | 2/5/2026 | Approved | JON MCHUGH |
| Final | 2/5/2026 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 2/5/2026 | Approved | JON MCHUGH |
| PLUMBING-Final | 2/5/2026 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Approved | JON MCHUGH |