1222 S GENESEE AVE 90019
Certificate Information: 1222 S GENESEE AVE 90019
- Application / Permit
- 24014-10000-02957
- Plan Check / Job No.
- B24LA12994
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL & ADDITION TO EXISTING ONE-STORY SINGLE FAMILY DWELLING & ENCLOSE (E) PATIO COVER
- Permit Issued
- Issued on 8/5/2024
- Issuing Office
- Current Status
- CofO Issued on 7/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 7/13/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 8/4/2024 | ALEC MOUSAKHANIAN |
| Issued | 8/5/2024 | APPLICANT |
| CofO in Progress | 6/19/2025 | ARTHUR NEGRETE |
| Permit Finaled | 7/5/2025 | DEROLD HAUFF |
| CofO Issued | 7/5/2025 | DEROLD HAUFF |
| Permit Finaled | 7/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/27/2024 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 7/27/2024 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2024 | JOSE HERNANDEZ |
Contact Information
| Contractor | Basix Designs & Remodeling Inc; Lic. No.: 769443-B | , |
| Engineer | Lin,, Jason; Lic. No.: S6095 | 801 CREST VISTA DR MONTEREY PARK, CA 91754 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/13/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 9/13/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Subgrade | 9/13/2024 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 12/23/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 12/23/2024 | Approved | ARTHUR NEGRETE |
| Gas Test | 12/23/2024 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 12/23/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 12/23/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Rough | 12/23/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 12/23/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 12/24/2024 | Corrections Issued | ANTHONY RAMOS |
| Insulation | 12/31/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 12/31/2024 | Approved | ALEX COLIN |
| Shower Pan | 12/31/2024 | Order to Comply Issued | ALEX COLIN |
| Drywall Nailing | 1/10/2025 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 6/18/2025 | Approved | ARTHUR NEGRETE |
| Final | 6/18/2025 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 6/18/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 6/18/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 6/18/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 6/18/2025 | Approved | ARTHUR NEGRETE |