4170 N SUNNYSLOPE AVE 91423

Certificate Information: 4170 N SUNNYSLOPE AVE 91423

Application / Permit
24014-10000-02942
Plan Check / Job No.
B24LA12925
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan 2-STORY ADDITIO AND MAJOR REMODEL (E) SFD ***FIRE SPRINKLER 13D REQUIRED*** 1 of 3
Permit Issued
Issued on 12/13/2024
Issuing Office
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 KHUONG TRUONG
Corrections Issued 7/18/2024 KHUONG TRUONG
Quality Review Completed 7/25/2024 GARO TELMI
Plan Check Approved 9/19/2024 KHUONG TRUONG
Issued 12/13/2024 APPLICANT
CofO in Progress 1/15/2026 JOSE AVILA
Permit Finaled 2/12/2026 RUBEN SALAS
CofO Issued 2/12/2026 RUBEN SALAS
Permit Finaled 2/12/2026 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 7/30/2024 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 8/2/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/2/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/2/2024 BIAINA HARITUNIAN
Permit Cleared 8/28/2024 BIAINA HARITUNIAN
Trees in Parkway Cleared 8/28/2024 ADALBERTO VERA
GPI Written Notices Cleared 9/19/2024 KHUONG TRUONG

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/18/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 2/20/2025 Partial Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 3/3/2025 Conditional Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/3/2025 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/5/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/5/2025 Partial Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/11/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Partial Approval MISAEL ESPARZA
Reinforced Masonry Frame 3/18/2025 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 4/28/2025 Corrections Issued MISAEL ESPARZA
HVAC-Rough 4/28/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 4/28/2025 Approved MISAEL ESPARZA
ELECTRICAL-Rough 4/30/2025 Approved MISAEL ESPARZA
Deputy Wood Construction 5/9/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 5/12/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 5/12/2025 Not Ready for Inspection MISAEL ESPARZA
Insulation 5/12/2025 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 5/13/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 5/21/2025 Approved JUAN VALENZUELA
Green Building Rough 5/21/2025 Approved JUAN VALENZUELA
Interior/Exterior Lathing 5/21/2025 Partial Approval JUAN VALENZUELA
Shower Pan 5/21/2025 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 5/21/2025 Approved JUAN VALENZUELA
Drywall Nailing 5/28/2025 Approved JUAN VALENZUELA
Interior/Exterior Lathing 5/28/2025 Approved JUAN VALENZUELA
ELECTRICAL-Final 10/15/2025 Not Ready for Inspection JUAN VALENZUELA
Final 10/15/2025 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 10/15/2025 Approved JUAN VALENZUELA
Green Building Final 10/15/2025 Not Ready for Inspection JUAN VALENZUELA
HVAC-Final 10/15/2025 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Final 10/15/2025 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 10/15/2025 Not Ready for Inspection JUAN VALENZUELA
Final 12/26/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 12/26/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/26/2025 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 12/26/2025 Approved JACK KARGODORIAN
Final 1/6/2026 Not Ready for Inspection JOSE AVILA
Final 1/14/2026 OK to Issue CofO JOSE AVILA
Service/Power Release 1/14/2026 Approved JOSE AVILA