5420 W 76TH ST 90045
Certificate Information: 5420 W 76TH ST 90045
- Application / Permit
- 24014-10000-02938
- Plan Check / Job No.
- B24LA12909
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT (E) REC ROOM AND (N) ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 7/1/2025
- Issuing Office
- Current Status
- CofO Issued on 1/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2024 | ISIS ARGUETA |
| Corrections Issued | 7/11/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 10/1/2024 | ISIS ARGUETA |
| Plan Check Approved | 10/3/2024 | EDWIN ESPIN |
| Issued | 7/1/2025 | APPLICANT |
| CofO in Progress | 1/13/2026 | JESUS PINEDA |
| Permit Finaled | 1/17/2026 | RICHARD STEINBACH |
| CofO Issued | 1/17/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/17/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/22/2024 | BRENDEN HAWK |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 7/27/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 7/27/2024 | LIAM ODONOVAN |
| Specific Plan | Cleared | 8/1/2024 | JACQUELINE TORRES |
| Grading Pre-Inspection | Cleared | 8/2/2024 | VASIL MIHALEV |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: NA24587 | , |
| Contractor | Coast Builders Group Inc; Lic. No.: 872035-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/11/2025 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 7/14/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 7/14/2025 | Partial Approval | ANTHONY EGSON |
| Sewer | 7/14/2025 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/16/2025 | No Access for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/21/2025 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 8/12/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 8/29/2025 | Approved | JESUS PINEDA |
| Green Building Rough | 8/29/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 8/29/2025 | Approved | JESUS PINEDA |
| Insulation | 8/29/2025 | Corrections Issued | JESUS PINEDA |
| MERV13>=Rough | 8/29/2025 | Approved | JESUS PINEDA |
| Insulation | 9/4/2025 | Partial Approval | RUBEN RIVAS |
| Shower Pan | 9/4/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 9/8/2025 | Approved | JAYLIN GRAVITTE |
| Insulation | 9/8/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 9/8/2025 | Approved | JAYLIN GRAVITTE |
| Special/Order Compliance | 9/8/2025 | Partial Inspection | HERBERT GIRON |
| Special/Order Compliance | 9/8/2025 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 11/7/2025 | Approved | JESUS PINEDA |
| Final | 11/7/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 11/7/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 11/7/2025 | Approved | JESUS PINEDA |
| MERV13>=Final | 11/7/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 11/7/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV Not Required | JESUS PINEDA |
| Service/Power Release | 11/7/2025 | Approved | JESUS PINEDA |
| Smoke Detectors | 11/7/2025 | Approved | JESUS PINEDA |
| Final | 11/21/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Green Building Final | 11/21/2025 | Approved | MEL KHACHATOURIAN |
| Final | 1/13/2026 | OK to Issue CofO | JESUS PINEDA |