12511 W WALSH AVE 90066
Certificate Information: 12511 W WALSH AVE 90066
- Application / Permit
- 24014-10000-02929
- Plan Check / Job No.
- B24LA12868
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Conversion of detached garage to ADU and porch addition per LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 12/9/2024
- Issuing Office
- Current Status
- CofO Issued on 11/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2024 | SAMUEL GONZALEZ |
| Corrections Issued | 7/12/2024 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 7/24/2024 | SAMUEL GONZALEZ |
| Plan Check Approved | 11/26/2024 | NEHEMIAS RAMOS |
| Issued | 12/9/2024 | APPLICANT |
| CofO in Progress | 11/7/2025 | RUBEN RIVAS |
| Permit Finaled | 11/20/2025 | RICHARD STEINBACH |
| CofO Issued | 11/20/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/20/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2024 | ANDREA SAINT-ANTONIN |
| Roof/Waste drainage to street | Cleared | 7/16/2024 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 7/16/2024 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 7/16/2024 | RICHARD WOO |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2024 | ANDREA SAINT-ANTONIN |
| Construction near power lines | Cleared | 11/2/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Schaefer,, Jeffrey; Lic. No.: C91734 | 3325 E 4TH ST LONG BEACH, CA 90814 |
| Engineer | Schaefer,, Jeffrey; Lic. No.: NA91734 | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 1/31/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 1/31/2025 | Approved | MICHAEL ALLEN |
| Sewer | 1/31/2025 | Approved | MICHAEL ALLEN |
| Deputy Drilled-In Anchors | 2/7/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 3/19/2025 | Corrections Issued | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Corrections Issued | RUBEN RIVAS |
| HVAC-Rough | 3/19/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Rough | 3/19/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 3/19/2025 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 3/24/2025 | Partial Approval | RUBEN RIVAS |
| HVAC-Rough | 3/24/2025 | Approved | RUBEN RIVAS |
| Insulation | 3/26/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Special/Order Compliance | 3/26/2025 | Partial Inspection | BOBBY KEY |
| Insulation | 3/28/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 3/28/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 4/8/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 4/8/2025 | Approved | RUBEN RIVAS |
| Shower Pan | 6/11/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 9/8/2025 | Approved | RUBEN RIVAS |
| Service/Power Release | 9/16/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 10/10/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 10/10/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 10/20/2025 | Approved | RUBEN RIVAS |
| Final | 10/20/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 10/20/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Not Ready | RUBEN RIVAS |
| Smoke Detectors | 10/20/2025 | Approved | RUBEN RIVAS |
| Final | 10/31/2025 | Corrections Issued | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Approved | RUBEN RIVAS |
| Final | 11/6/2025 | OK to Issue CofO | RUBEN RIVAS |
| Service/Power Release | 11/6/2025 | Approved | RUBEN RIVAS |