614 N CAHUENGA BLVD 90004

Certificate Information: 614 N CAHUENGA BLVD 90004

Application / Permit
24014-10000-02928
Plan Check / Job No.
B24LA12861
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW REAR ADDITION TO THE (E) SINGLE FAMILY DWELLING. INTERIOR REMODELING TO THE (E) SINGLE FAMILY DWELLING. CHANGE OUT WINDOWS, ADD DOORS.
Permit Issued
Issued on 1/16/2025
Issuing Office
Current Status
CofO Issued on 9/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2024 APPLICANT
Assigned to Plan Check Engineer 7/12/2024 GIOVANNY CHAVEZ
Corrections Issued 7/13/2024 GIOVANNY CHAVEZ
Plan Check Approved 1/15/2025 GIOVANNY CHAVEZ
Issued 1/16/2025 APPLICANT
CofO in Progress 9/25/2025 JEFFREY MEAD
Permit Finaled 9/27/2025 DEROLD HAUFF
CofO Issued 9/27/2025 DEROLD HAUFF
Permit Finaled 9/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/20/2024 CHRISTINA BRACO
Sewer availability Cleared 11/20/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 11/21/2024 CHRISTINA BRACO
HPOZ Cleared 12/17/2024 SUKI GERSHENHORN

Contact Information

Architect Duffy,, Robert K; Lic. No.: NA7604       ,
Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/19/2025 Conditional Approval JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 2/20/2025 Corrections Issued JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval RONNIE MINDANAO
Insulation 3/4/2025 Partial Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Partial Approval JEFFREY MEAD
Green Building Rough 4/15/2025 Not Ready for Inspection JEFFREY MEAD
METHANE-Rough 4/15/2025 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Final 6/4/2025 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 6/4/2025 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Approved BRENDAN MORELLI
Green Building Rough 6/4/2025 Not Ready for Inspection BRENDAN MORELLI
METHANE-Rough 6/4/2025 Approved BRENDAN MORELLI
PLUMBING-Rough 6/4/2025 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 6/9/2025 Corrections Issued JEFFREY MEAD
Green Building Rough 6/9/2025 Approved JEFFREY MEAD
Interior/Exterior Lathing 6/9/2025 Partial Approval JEFFREY MEAD
Insulation 6/13/2025 Approved JEFFREY MEAD
Drywall Nailing 6/27/2025 Approved ALEX COLIN
Shower Pan 7/15/2025 Approved JEFFREY MEAD
Interior/Exterior Lathing 7/18/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 9/16/2025 Approved JEFFREY MEAD
Final 9/16/2025 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 9/16/2025 Approved JEFFREY MEAD
Green Building Final 9/16/2025 Approved JEFFREY MEAD
METHANE-Barrier 9/16/2025 Approved JEFFREY MEAD
METHANE-Subgrade 9/16/2025 Approved JEFFREY MEAD
Pre-Inspection 9/16/2025 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Approved JEFFREY MEAD
Smoke Detectors 9/16/2025 Approved JEFFREY MEAD
Final 9/24/2025 OK to Issue CofO JEFFREY MEAD