3423 W FERNCROFT ROAD 90039

Certificate Information: 3423 W FERNCROFT ROAD 90039

Application / Permit
24014-10000-02902
Plan Check / Job No.
B24LA12724
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan:PROPOSED ADDITION AND INTERIOR REMODEL TO EXISTING SINGLE FAMILY DWELLING. 1 OF 2
Permit Issued
Issued on 1/3/2025
Issuing Office
Current Status
CofO Issued on 4/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 MICHAEL LOPEZ
Corrections Issued 8/5/2024 MICHAEL LOPEZ
Quality Review Completed 8/8/2024 GARO TELMI
Applicant returned to address corrections 9/17/2024 MICHAEL LOPEZ
Applicant returned to address corrections 11/1/2024 MICHAEL LOPEZ
Plan Check Approved 12/19/2024 MICHAEL LOPEZ
Issued 1/3/2025 APPLICANT
CofO in Progress 4/9/2026 NICHOLAS LOPEZ
Permit Finaled 4/10/2026 DEROLD HAUFF
Permit Finaled 4/10/2026 DEROLD HAUFF
CofO Issued 4/10/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/15/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 8/15/2024 DAVID LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/3/2025 Corrections Issued NICHOLAS LOPEZ
Underground Mechanical 3/5/2025 Partial Approval NICHOLAS LOPEZ
Deputy Drilled-In Anchors 3/10/2025 Conditional Approval NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 3/11/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/9/2025 Partial Approval NICHOLAS LOPEZ
ELECTRICAL-Rough 9/15/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 9/15/2025 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Rough 9/29/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 10/9/2025 Approved NICHOLAS LOPEZ
Green Building Rough 10/9/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 10/9/2025 Approved NICHOLAS LOPEZ
MERV13>=Rough 10/9/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 10/9/2025 Approved NICHOLAS LOPEZ
Insulation 10/23/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Corrections Issued NICHOLAS LOPEZ
Drywall Nailing 12/17/2025 Not Ready for Inspection NICHOLAS LOPEZ
Shower Pan 12/17/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 12/22/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 12/24/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 2/24/2026 Corrections Issued NICHOLAS LOPEZ
HVAC-Final 2/24/2026 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 2/24/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 3/6/2026 Approved NICHOLAS LOPEZ
HVAC-Final 3/6/2026 Approved NICHOLAS LOPEZ
Special/Order Compliance 3/6/2026 Corrections Issued NICHOLAS LOPEZ
Final 3/11/2026 Corrections Issued NICHOLAS LOPEZ
Footing/Foundation/Slab 3/11/2026 Approved NICHOLAS LOPEZ
Green Building Final 3/11/2026 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 3/11/2026 Approved NICHOLAS LOPEZ
MERV13>=Final 3/11/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/11/2026 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 3/11/2026 Approved NICHOLAS LOPEZ
Final 4/8/2026 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 4/8/2026 Approved NICHOLAS LOPEZ