4305 N GREENBUSH AVE 91423
Certificate Information: 4305 N GREENBUSH AVE 91423
- Application / Permit
- 24014-10000-02899
- Plan Check / Job No.
- B24LA12708
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE TO A NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) WITH NEW 4'-7 3/8" X 13'6" PATIO COVER ADDITION ATTACHED TO ADU. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 10/22/2024
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2024 | KAMYAR EMAMI |
| Corrections Issued | 7/10/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 7/25/2024 | MADISON ODELL |
| Applicant returned to address corrections | 8/8/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 8/13/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 8/16/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 9/10/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 10/10/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 10/22/2024 | MIROOSH KHACHATOORIAN |
| Issued | 10/22/2024 | APPLICANT |
| CofO in Progress | 6/9/2025 | MISAEL ESPARZA |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 7/13/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 10/18/2024 | TINA MIRANDA |
Contact Information
| Contractor | Modative Build Inc; Lic. No.: 957698-B | , |
| Contractor | Modative Build, Inc; Lic. No.: 957698-B | , |
| Engineer | Sveiven,, Shane; Lic. No.: C89133 | 1909 S ALMA STREET SAN PEDRO, CA 90731 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/25/2024 | Approved | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 11/1/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 11/5/2024 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 11/14/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/19/2024 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 11/25/2024 | Partial Approval | MISAEL ESPARZA |
| Sewer | 11/25/2024 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 12/5/2024 | Conditional Approval | JUAN VALENZUELA |
| Sewer | 12/5/2024 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/10/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/16/2025 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 1/16/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 1/16/2025 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 1/28/2025 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 1/31/2025 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 2/3/2025 | Approved | MISAEL ESPARZA |
| Insulation | 2/6/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/6/2025 | Approved | MISAEL ESPARZA |
| Shower Pan | 2/6/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 2/10/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/29/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 5/29/2025 | Approved | JACK KARGODORIAN |
| Final | 5/29/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 5/29/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 5/29/2025 | Approved | JACK KARGODORIAN |
| HVAC-Final | 5/29/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 5/29/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 5/29/2025 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 5/29/2025 | Approved | JACK KARGODORIAN |
| Final | 6/6/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 6/6/2025 | Approved | MISAEL ESPARZA |