2250 S PROSSER AVE 90064
Certificate Information: 2250 S PROSSER AVE 90064
- Application / Permit
- 24014-10000-02895
- Plan Check / Job No.
- B24LA12696
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO REAR OF (E) SFD TO EXTEND ONE BEDROOM, BATHROOM, ADD A CLOSET. REMODEL OF ENTIRE SFD TO RELOCATE ONE BATHROOM, RELOCATE WASHER/ DRYER. ALL WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 1/23/2025
- Issuing Office
- Current Status
- CofO Issued on 11/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2024 | MADISON ODELL |
| Corrections Issued | 7/9/2024 | MADISON ODELL |
| Applicant returned to address corrections | 11/13/2024 | MADISON ODELL |
| Applicant returned to address corrections | 12/11/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 1/17/2025 | PINANK PATEL |
| Applicant returned to address corrections | 1/21/2025 | PINANK PATEL |
| Plan Check Approved | 1/22/2025 | PINANK PATEL |
| Issued | 1/23/2025 | APPLICANT |
| CofO in Progress | 11/13/2025 | DANIEL VERA |
| Permit Finaled | 11/19/2025 | RICHARD STEINBACH |
| CofO Issued | 11/19/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/19/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/25/2024 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2024 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 8/5/2024 | FREDDY GARCIA |
| Roof/Waste drainage to street | Cleared | 12/10/2024 | KIMBERLY HERNANDEZ |
| Flood clearance | Cleared | 1/15/2025 | TUYEN LE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manesh,, Behnam Abraham; Lic. No.: NA38454 | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/21/2025 | Conditional Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 2/24/2025 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 2/25/2025 | Partial Approval | SEAN HAUPT |
| FLOOD-Elevation Certificate | 3/4/2025 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 3/4/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/4/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 3/7/2025 | Partial Inspection | WILBER ROSALES |
| BUILDING-Rough-Frame | 4/24/2025 | Not Ready for Inspection | DANIEL VERA |
| Deputy Drilled-In Anchors | 4/24/2025 | Conditional Approval | DANIEL VERA |
| ELECTRICAL-Rough | 4/24/2025 | Corrections Issued | DANIEL VERA |
| FLOOD-Proofing Certificate | 4/24/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 4/24/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 4/24/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 4/24/2025 | Approved | DANIEL VERA |
| HVAC-Rough | 4/25/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Approved | DANIEL VERA |
| PLUMBING-Rough | 4/29/2025 | Approved | DANIEL VERA |
| Special/Order Compliance | 4/29/2025 | Corrections Issued | DANIEL VERA |
| BUILDING-Rough-Frame | 5/2/2025 | Conditional Approval | DANIEL VERA |
| FLOOD-Proofing Certificate | 5/2/2025 | Conditional Approval | DANIEL VERA |
| Green Building Rough | 5/2/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 5/2/2025 | Partial Approval | DANIEL VERA |
| Insulation | 5/9/2025 | Not Ready for Inspection | DANIEL VERA |
| Deputy Wood Construction | 5/14/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Insulation | 5/15/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/15/2025 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 5/15/2025 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 5/29/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 8/27/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 8/27/2025 | Approved | DANIEL VERA |
| FLOOD-Proofing Certificate | 8/27/2025 | Approved | DANIEL VERA |
| Final | 8/27/2025 | Not Ready for Inspection | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 8/27/2025 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 8/27/2025 | Approved | DANIEL VERA |
| HVAC-Final | 8/28/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 8/28/2025 | Approved | DANIEL VERA |
| Final | 9/2/2025 | Corrections Issued | DANIEL VERA |
| Green Building Final | 9/2/2025 | Approved | DANIEL VERA |
| Final | 9/25/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 11/12/2025 | OK to Issue CofO | DANIEL VERA |
| HVAC-Final | 11/12/2025 | Approved | DANIEL VERA |
| Service/Power Release | 11/12/2025 | Approved | DANIEL VERA |