5933 E TIPTON WAY 90042
Certificate Information: 5933 E TIPTON WAY 90042
- Application / Permit
- 24014-10000-02894
- Plan Check / Job No.
- B24LA12687
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- EPLAN. NEW DETACHED STORAGE PER WFPP
- Permit Issued
- Issued on 9/11/2024
- Issuing Office
- Current Status
- CofO Issued on 11/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 7/6/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 7/12/2024 | TU HUA |
| Quality Review Completed | 7/12/2024 | TU HUA |
| Applicant returned to address corrections | 8/29/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 9/10/2024 | MARCELA FRANQUEZ |
| Issued | 9/11/2024 | APPLICANT |
| CofO in Progress | 10/17/2024 | ROY SPAULDING |
| No Progress | 11/14/2024 | DEROLD HAUFF |
| CofO in Progress | 11/14/2024 | DEROLD HAUFF |
| CofO in Progress | 11/15/2024 | CHARLES BOGHOSKHAN |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
| CofO Issued | 11/16/2024 | DEROLD HAUFF |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/8/2024 | MARCELA FRANQUEZ |
| Tenant Habitability Plan | Cleared | 7/16/2024 | RICARDO BOHORQUEZ |
| Roof/Waste drainage to street | Cleared | 7/18/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 7/18/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/23/2024 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 10/7/2024 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 10/7/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 10/7/2024 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 10/7/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 10/11/2024 | Approved | ROY SPAULDING |
| Final | 10/11/2024 | Conditional Approval | ROY SPAULDING |
| Green Building Final | 10/11/2024 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Approved | ROY SPAULDING |
| Service/Power Release | 10/11/2024 | Approved | ROY SPAULDING |
| Smoke Detectors | 10/11/2024 | Approved | ROY SPAULDING |
| Final | 10/16/2024 | OK to Issue CofO | ROY SPAULDING |