4536 N COLLEGE VIEW AVE 90041
Certificate Information: 4536 N COLLEGE VIEW AVE 90041
- Application / Permit
- 24014-10000-02891
- Plan Check / Job No.
- B24LA12673
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 9'-0" X 17'-5" ENCLOSURE OF EXISTING COVERED PORCH AND CONVERT TO LAUNDRY ROOM - PER ENGINEER
- Permit Issued
- Issued on 8/16/2024
- Issuing Office
- Current Status
- Issued on 8/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 7/10/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 8/7/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 8/15/2024 | DANIEL ABRAMYAN |
| Issued | 8/16/2024 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/10/2024 | DANIEL ABRAMYAN |
| Roof/Waste drainage to street | Cleared | 7/23/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2024 | JUSTIN BICOL |
| ZA Case | Cleared | 7/25/2024 | ALEX VELA |
| ZA Case | Cleared | 7/25/2024 | ALEX VELA |
Contact Information
| Contractor | Hexagon Construction; Lic. No.: 1082693-B | , |
| Contractor | Tke Leadership Inc; Lic. No.: 1082693-B | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 5306 MULHOLLAND DRIVE SUMMERVILLE, SC 29485 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/4/2024 | Corrections Issued | ROY SPAULDING |
| Deputy Drilled-In Anchors | 9/5/2024 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 9/10/2024 | Not Ready for Inspection | ROY SPAULDING |
| Wood Frame | 9/10/2024 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 9/12/2024 | Corrections Issued | ROY SPAULDING |
| Green Building Rough | 9/12/2024 | Not Ready for Inspection | ROY SPAULDING |
| Wood Frame | 9/12/2024 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 9/26/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 9/26/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 9/26/2024 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 9/26/2024 | Corrections Issued | ROY SPAULDING |
| Wood Frame | 9/26/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 9/30/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 9/30/2024 | Approved | ROY SPAULDING |
| Insulation | 10/3/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 10/3/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 10/7/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 10/7/2024 | Approved | ROY SPAULDING |