615 1/2 E 25TH ST 90011

Certificate Information: 615 1/2 E 25TH ST 90011

Application / Permit
24014-10000-02886
Plan Check / Job No.
B24LA12649
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT (E) GARAGE TO 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 12/6/2024
Issuing Office
Metro
Current Status
CofO Issued on 11/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 DANIEL YIP
Corrections Issued 7/31/2024 DANIEL YIP
Quality Review Completed 8/2/2024 KEN GILL
Building Plans Picked Up 8/12/2024 APPLICANT
Plan Check Approved 8/22/2024 DANIEL YIP
Issued 12/6/2024 APPLICANT
CofO in Progress 11/14/2025 ALEJANDRO DE ARTOLA
Permit Finaled 11/16/2025 DEROLD HAUFF
CofO Issued 11/16/2025 DEROLD HAUFF
Permit Finaled 11/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/13/2024 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 8/13/2024 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 8/14/2024 ADRIAN SANCHEZ
Sewer availability Cleared 8/14/2024 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 1/16/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 1/16/2025 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 1/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 3/24/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 5/19/2025 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 5/22/2025 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 6/4/2025 Conditional Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 6/6/2025 Conditional Approval ANTHONY RAMOS
Interior/Exterior Lathing 6/10/2025 Partial Approval REGINA MENDEZ
PLUMBING-Rough 6/11/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 6/13/2025 Approved REGINA MENDEZ
ELECTRICAL-Rough 7/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 7/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 7/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 7/21/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 7/22/2025 Approved ALEJANDRO DE ARTOLA
Insulation 7/28/2025 Approved RONNIE MEDINA
BUILDING-Rough-Frame 7/30/2025 Conditional Approval NICHOLAS LOPEZ
HVAC-Rough 7/30/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 8/12/2025 Not Ready for Inspection RONNIE MEDINA
Drywall Nailing 8/13/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/22/2025 Corrections Issued RONNIE MEDINA
Interior/Exterior Lathing 8/25/2025 Approved RONNIE MEDINA
BUILDING-Rough-Frame 9/3/2025 Approved ALEJANDRO DE ARTOLA
Final 9/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/3/2025 Approved ALEJANDRO DE ARTOLA
Green Building Final 9/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 9/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/5/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 9/5/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 9/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 9/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 9/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 9/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/1/2025 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Final 10/1/2025 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 10/1/2025 Corrections Issued ENRIQUE MIRELES
Final 10/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/7/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 10/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 10/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 10/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/4/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Pre-Inspection 11/5/2025 Approved ALEJANDRO DE ARTOLA
Final 11/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 11/6/2025 Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 11/7/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Final 11/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 11/13/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/14/2025 Approved ALEJANDRO DE ARTOLA
Final 11/14/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
PLUMBING-Final 11/14/2025 Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/14/2025 Approved ALEJANDRO DE ARTOLA