1448 N LAVETA TER 90026

Certificate Information: 1448 N LAVETA TER 90026

Application / Permit
24014-10000-02884
Plan Check / Job No.
B24LA12645
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO EXISTING SINGLE FAMILY RESIDENCE
Permit Issued
Issued on 8/14/2024
Issuing Office
Metro
Current Status
Issued on 8/14/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/2/2024 APPLICANT
Assigned to Plan Check Engineer 7/3/2024 WEIJIAN HUANG
Corrections Issued 7/10/2024 WEIJIAN HUANG
Quality Review Completed 7/16/2024 DANIEL CHAN
Building Plans Picked Up 7/18/2024 APPLICANT
Applicant returned to address corrections 8/1/2024 WEIJIAN HUANG
Plan Check Approved 8/7/2024 WEIJIAN HUANG
Issued 8/14/2024 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/10/2024 WEIJIAN HUANG
Roof/Waste drainage to street Cleared 7/18/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 7/22/2024 TREVOR QUAN

Contact Information

Contractor Requiem Builders & Design; Lic. No.: 1055466-B 2406 ELMGROVE STREET      LOS ANGELES, CA 90031
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/16/2024 Corrections Issued WILLIAM SIERRA
Pre-Inspection 8/16/2024 Corrections Issued WILLIAM SIERRA
Excavation/Setback/Form/Re-Bar 8/20/2024 Not Ready for Inspection LUIS CASTRO
Excavation/Setback/Form/Re-Bar 8/22/2024 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/22/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 8/23/2024 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/26/2024 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 10/16/2024 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/17/2024 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 10/17/2024 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Approved LUIS CASTRO
Green Building Rough 10/17/2024 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 10/17/2024 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 10/17/2024 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 10/21/2024 Approved LUIS CASTRO
HVAC-Rough 10/21/2024 Corrections Issued LUIS CASTRO
BUILDING-Rough-Frame 10/22/2024 Not Ready for Inspection LUIS CASTRO
Green Building Rough 10/22/2024 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 10/22/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 10/25/2024 Partial Approval WILLIAM SIERRA
BUILDING-Rough-Frame 10/28/2024 Approved JOHN QUINTANILLA
Green Building Rough 10/28/2024 Approved JOHN QUINTANILLA
Insulation 10/28/2024 Not Ready for Inspection JOHN QUINTANILLA
Insulation 10/31/2024 Approved LUIS CASTRO
Drywall Nailing 11/4/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Drywall Nailing 11/7/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/2/2024 Partial Approval HAMIK HARTOUNIAN
Shower Pan 12/2/2024 Approved HAMIK HARTOUNIAN
Final 1/2/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/2/2025 Approved HAMIK HARTOUNIAN
Green Building Final 1/2/2025 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/2/2025 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 1/2/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 1/3/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 1/3/2025 Corrections Issued HAMIK HARTOUNIAN
Final 1/15/2025 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 1/15/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV No Gas HAMIK HARTOUNIAN
Smoke Detectors 1/15/2025 Approved HAMIK HARTOUNIAN